Creek Rise construction photos

139 photos from 15 site inspections, newest first. The percentage is how much of Creek Rise was built on the day of each visit.

29 December 2021100% built

4 October 202196% built

29 June 202193% built

11 March 202187% built

24 November 202080% built

31 August 202074% built

11 May 202068% built

29 October 201960% built

25 July 201942% built

11 April 201934% built

27 December 201824% built

14 August 201815% built

2 May 201811% built

17 January 20184.8% built

25 October 20170.3% built

Back to Creek Rise construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.