Creek Palace construction progress

The register lists Creek Palace in Dubai Creek Harbour as complete, with a registered completion date of March 2026. Its last site inspection on record was in November 2024. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 15 November 2024

Construction complete

Registered completion date
March 2026
Construction started
January 2020
First registered
January 2020
Units
337
Escrow bank
Emirates NBD
Name in Arabic
كريك بالاس
Project number
2191
Site inspections
7

Schedule

The register lists Creek Palace as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 November 2024

100%+7.8 pts

  • Creek Palace construction site, inspection photo 1, 15 November 2024
  • Creek Palace construction site, inspection photo 2, 15 November 2024
  • Creek Palace construction site, inspection photo 3, 15 November 2024
  • Creek Palace construction site, inspection photo 4, 15 November 2024

2 September 2024

92%+37 pts

  • Creek Palace construction site, inspection photo 1, 2 September 2024
  • Creek Palace construction site, inspection photo 2, 2 September 2024
  • Creek Palace construction site, inspection photo 3, 2 September 2024
  • Creek Palace construction site, inspection photo 4, 2 September 2024

12 March 2024

55%+28 pts

  • Creek Palace construction site, inspection photo 1, 12 March 2024
  • Creek Palace construction site, inspection photo 2, 12 March 2024
  • Creek Palace construction site, inspection photo 3, 12 March 2024
  • Creek Palace construction site, inspection photo 4, 12 March 2024

6 October 2023

27%+12 pts

  • Creek Palace construction site, inspection photo 1, 6 October 2023
  • Creek Palace construction site, inspection photo 2, 6 October 2023
  • Creek Palace construction site, inspection photo 3, 6 October 2023
  • Creek Palace construction site, inspection photo 4, 6 October 2023

8 June 2023

15%+7.4 pts

  • Creek Palace construction site, inspection photo 1, 8 June 2023
  • Creek Palace construction site, inspection photo 2, 8 June 2023
  • Creek Palace construction site, inspection photo 3, 8 June 2023
  • Creek Palace construction site, inspection photo 4, 8 June 2023

31 January 2023

7.8%+3.7 pts

  • Creek Palace construction site, inspection photo 1, 31 January 2023
  • Creek Palace construction site, inspection photo 2, 31 January 2023
  • Creek Palace construction site, inspection photo 3, 31 January 2023
  • Creek Palace construction site, inspection photo 4, 31 January 2023

13 October 2022

4.1%

  • Creek Palace construction site, inspection photo 1, 13 October 2022
  • Creek Palace construction site, inspection photo 2, 13 October 2022
  • Creek Palace construction site, inspection photo 3, 13 October 2022
  • Creek Palace construction site, inspection photo 4, 13 October 2022

All 50 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Palace?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Palace handover date?
Construction of Creek Palace is recorded as complete, with a registered completion date of March 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Palace?
Creek Palace was 100% built at the site inspection on 15 November 2024. The site has been inspected 7 times since October 2022. The Land Department took 50 site photos at its inspections.
Is Creek Palace delayed?
The register lists construction as complete.
Who is building Creek Palace?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Palace?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.