Creek Palace construction photos
50 photos from 7 site inspections, newest first. The percentage is how much of Creek Palace was built on the day of each visit.
15 November 2024100% built
2 September 202492% built
12 March 202455% built
6 October 202327% built
8 June 202315% built
31 January 20237.8% built
13 October 20224.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.