Creek Edge construction progress

The register lists Creek Edge in Dubai Creek Harbour as complete, with a registered completion date of September 2023. Its last site inspection on record was in October 2023. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 3 October 2023

Construction complete

Registered completion date
September 2023
Construction started
August 2019
First registered
August 2018
Units
564
Escrow bank
Emirates NBD
Name in Arabic
كريك ايدج
Project number
2083
Site inspections
10

Schedule

The register lists Creek Edge as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 October 2023

100%+5.2 pts

  • Creek Edge construction site, inspection photo 1, 3 October 2023
  • Creek Edge construction site, inspection photo 2, 3 October 2023
  • Creek Edge construction site, inspection photo 3, 3 October 2023
  • Creek Edge construction site, inspection photo 4, 3 October 2023

8 August 2023

95%+3.1 pts

  • Creek Edge construction site, inspection photo 1, 8 August 2023
  • Creek Edge construction site, inspection photo 2, 8 August 2023
  • Creek Edge construction site, inspection photo 3, 8 August 2023
  • Creek Edge construction site, inspection photo 4, 8 August 2023

6 July 2023

92%+9.2 pts

  • Creek Edge construction site, inspection photo 1, 6 July 2023
  • Creek Edge construction site, inspection photo 2, 6 July 2023
  • Creek Edge construction site, inspection photo 3, 6 July 2023
  • Creek Edge construction site, inspection photo 4, 6 July 2023

15 March 2023

82%+17 pts

  • Creek Edge construction site, inspection photo 1, 15 March 2023
  • Creek Edge construction site, inspection photo 2, 15 March 2023
  • Creek Edge construction site, inspection photo 3, 15 March 2023
  • Creek Edge construction site, inspection photo 4, 15 March 2023

2 September 2022

65%+20 pts

  • Creek Edge construction site, inspection photo 1, 2 September 2022
  • Creek Edge construction site, inspection photo 2, 2 September 2022
  • Creek Edge construction site, inspection photo 3, 2 September 2022
  • Creek Edge construction site, inspection photo 4, 2 September 2022

13 May 2022

45%+19 pts

  • Creek Edge construction site, inspection photo 1, 13 May 2022
  • Creek Edge construction site, inspection photo 2, 13 May 2022
  • Creek Edge construction site, inspection photo 3, 13 May 2022
  • Creek Edge construction site, inspection photo 4, 13 May 2022

6 January 2022

27%+6.0 pts

  • Creek Edge construction site, inspection photo 1, 6 January 2022
  • Creek Edge construction site, inspection photo 2, 6 January 2022
  • Creek Edge construction site, inspection photo 3, 6 January 2022
  • Creek Edge construction site, inspection photo 4, 6 January 2022

10 November 2021

21%+7.8 pts

  • Creek Edge construction site, inspection photo 1, 10 November 2021
  • Creek Edge construction site, inspection photo 2, 10 November 2021
  • Creek Edge construction site, inspection photo 3, 10 November 2021
  • Creek Edge construction site, inspection photo 4, 10 November 2021

24 August 2021

13%+9.9 pts

  • Creek Edge construction site, inspection photo 1, 24 August 2021
  • Creek Edge construction site, inspection photo 2, 24 August 2021
  • Creek Edge construction site, inspection photo 3, 24 August 2021
  • Creek Edge construction site, inspection photo 4, 24 August 2021

2 March 2020

3.1%

  • Creek Edge construction site, inspection photo 1, 2 March 2020
  • Creek Edge construction site, inspection photo 2, 2 March 2020
  • Creek Edge construction site, inspection photo 3, 2 March 2020
  • Creek Edge construction site, inspection photo 4, 2 March 2020

All 113 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Edge?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Edge handover date?
Construction of Creek Edge is recorded as complete, with a registered completion date of September 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Edge?
Creek Edge was 100% built at the site inspection on 3 October 2023. The site has been inspected 10 times since March 2020. The Land Department took 113 site photos at its inspections.
Is Creek Edge delayed?
The register lists construction as complete.
Who is building Creek Edge?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Edge?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.