Creek Edge construction photos

113 photos from 10 site inspections, newest first. The percentage is how much of Creek Edge was built on the day of each visit.

3 October 2023100% built

8 August 202395% built

6 July 202392% built

15 March 202382% built

2 September 202265% built

13 May 202245% built

6 January 202227% built

10 November 202121% built

24 August 202113% built

2 March 20203.1% built

Back to Creek Edge construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.