Altan construction progress
Altan in Dubai Creek Harbour is 11% built at the Land Department inspection of July 2026. Developer Dubai Creek Harbour. Completion registered for July 2029.
11%
Built, at the Land Department site inspection of 2 July 2026
Running behind its date
- Completion date (Land Department)
- July 2029
- Finish at recent pace
- January 2037
- Construction started
- June 2025
- Registered with the Land Department
- March 2025
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour
- Units
- 479
- Escrow bank
- Emirates NBD
- Name in Arabic
- التان
- Land Department project number
- 3608
- Land Department site inspections
- 5
Schedule
Between September 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around January 2037, more than three months after the July 2029 date registered with the Land Department.
Site inspections
2 July 2026
11%+1.8 pts
17 March 2026
9.3%+2.5 pts
31 December 2025
6.7%+2.3 pts
19 September 2025
4.4%+4.4 pts
17 March 2025
0%
Context
Dubai Creek Harbour has 14 projects under construction, 41% built on average.
Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Altan?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Altan be completed?
- The completion date registered with the Dubai Land Department is July 2029. At the pace of its recent inspections the site would reach 100% around January 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Altan is built?
- 11%, measured at the Land Department site inspection on 2 July 2026. The Land Department engineers have inspected the site 5 times since March 2025.
- Is Altan delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
- Who is building Altan?
- The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
- Which bank holds the escrow account for Altan?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AeonAlso by Dubai Creek Harbour. 90%.
- OriaAlso by Dubai Creek Harbour. 71%.
- ValoAlso by Dubai Creek Harbour. 66%.
- ArloAlso by Dubai Creek Harbour. 35%.
- Creek WatersNearby in Dubai Creek Harbour. 81%, Due September 2027.
- Creek Waters 2Nearby in Dubai Creek Harbour. 82%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)