Altan construction progress

Altan in Dubai Creek Harbour is 11% built at the Land Department inspection of July 2026. Developer Dubai Creek Harbour. Completion registered for July 2029.

11%

Built, at the Land Department site inspection of 2 July 2026

Running behind its date

Completion date (Land Department)
July 2029
Finish at recent pace
January 2037
Construction started
June 2025
Registered with the Land Department
March 2025
Units
479
Escrow bank
Emirates NBD
Name in Arabic
التان
Land Department project number
3608
Land Department site inspections
5

Schedule

Between September 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around January 2037, more than three months after the July 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 July 2026

11%+1.8 pts

  • Altan construction site, Land Department inspection photo 1, 2 July 2026
  • Altan construction site, Land Department inspection photo 2, 2 July 2026
  • Altan construction site, Land Department inspection photo 3, 2 July 2026
  • Altan construction site, Land Department inspection photo 4, 2 July 2026

17 March 2026

9.3%+2.5 pts

  • Altan construction site, Land Department inspection photo 1, 17 March 2026
  • Altan construction site, Land Department inspection photo 2, 17 March 2026
  • Altan construction site, Land Department inspection photo 3, 17 March 2026
  • Altan construction site, Land Department inspection photo 4, 17 March 2026

31 December 2025

6.7%+2.3 pts

  • Altan construction site, Land Department inspection photo 1, 31 December 2025
  • Altan construction site, Land Department inspection photo 2, 31 December 2025
  • Altan construction site, Land Department inspection photo 3, 31 December 2025
  • Altan construction site, Land Department inspection photo 4, 31 December 2025

19 September 2025

4.4%+4.4 pts

  • Altan construction site, Land Department inspection photo 1, 19 September 2025
  • Altan construction site, Land Department inspection photo 2, 19 September 2025
  • Altan construction site, Land Department inspection photo 3, 19 September 2025
  • Altan construction site, Land Department inspection photo 4, 19 September 2025

17 March 2025

0%

  • Altan construction site, Land Department inspection photo 1, 17 March 2025
  • Altan construction site, Land Department inspection photo 2, 17 March 2025

All 22 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 41% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Altan?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Altan be completed?
The completion date registered with the Dubai Land Department is July 2029. At the pace of its recent inspections the site would reach 100% around January 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Altan is built?
11%, measured at the Land Department site inspection on 2 July 2026. The Land Department engineers have inspected the site 5 times since March 2025.
Is Altan delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Altan?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Altan?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.