Altan construction photos

22 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Altan was built on the day of each visit.

2 July 202611% built

17 March 20269.3% built

31 December 20256.7% built

19 September 20254.4% built

17 March 20250% built

Back to Altan construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.