Address Harbour Point construction progress

The register lists Address Harbour Point in Dubai Creek Harbour as complete, with a registered completion date of January 2023. Its last site inspection on record was in January 2023. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 12 January 2023

Construction complete

Registered completion date
January 2023
Construction started
June 2017
First registered
March 2017
Units
814
Escrow bank
Emirates NBD
Name in Arabic
العنوان هاربر بوينت
Project number
1870
Site inspections
15

Schedule

The register lists Address Harbour Point as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 January 2023

100%+6.0 pts

  • Address Harbour Point construction site, inspection photo 1, 12 January 2023
  • Address Harbour Point construction site, inspection photo 2, 12 January 2023
  • Address Harbour Point construction site, inspection photo 3, 12 January 2023
  • Address Harbour Point construction site, inspection photo 4, 12 January 2023

19 September 2022

94%+4.0 pts

  • Address Harbour Point construction site, inspection photo 1, 19 September 2022
  • Address Harbour Point construction site, inspection photo 2, 19 September 2022
  • Address Harbour Point construction site, inspection photo 3, 19 September 2022
  • Address Harbour Point construction site, inspection photo 4, 19 September 2022

23 May 2022

90%+8.0 pts

  • Address Harbour Point construction site, inspection photo 1, 23 May 2022
  • Address Harbour Point construction site, inspection photo 2, 23 May 2022
  • Address Harbour Point construction site, inspection photo 3, 23 May 2022
  • Address Harbour Point construction site, inspection photo 4, 23 May 2022

29 December 2021

82%+6.8 pts

  • Address Harbour Point construction site, inspection photo 1, 29 December 2021
  • Address Harbour Point construction site, inspection photo 2, 29 December 2021
  • Address Harbour Point construction site, inspection photo 3, 29 December 2021
  • Address Harbour Point construction site, inspection photo 4, 29 December 2021

20 October 2021

75%+13 pts

  • Address Harbour Point construction site, inspection photo 1, 20 October 2021
  • Address Harbour Point construction site, inspection photo 2, 20 October 2021
  • Address Harbour Point construction site, inspection photo 3, 20 October 2021
  • Address Harbour Point construction site, inspection photo 4, 20 October 2021

13 July 2021

63%+11 pts

  • Address Harbour Point construction site, inspection photo 1, 13 July 2021
  • Address Harbour Point construction site, inspection photo 2, 13 July 2021
  • Address Harbour Point construction site, inspection photo 3, 13 July 2021
  • Address Harbour Point construction site, inspection photo 4, 13 July 2021

7 April 2021

52%+9.9 pts

  • Address Harbour Point construction site, inspection photo 1, 7 April 2021
  • Address Harbour Point construction site, inspection photo 2, 7 April 2021
  • Address Harbour Point construction site, inspection photo 3, 7 April 2021
  • Address Harbour Point construction site, inspection photo 4, 7 April 2021

30 December 2020

42%+8.5 pts

  • Address Harbour Point construction site, inspection photo 1, 30 December 2020
  • Address Harbour Point construction site, inspection photo 2, 30 December 2020
  • Address Harbour Point construction site, inspection photo 3, 30 December 2020
  • Address Harbour Point construction site, inspection photo 4, 30 December 2020

2 September 2020

33%+5.7 pts

  • Address Harbour Point construction site, inspection photo 1, 2 September 2020
  • Address Harbour Point construction site, inspection photo 2, 2 September 2020
  • Address Harbour Point construction site, inspection photo 3, 2 September 2020
  • Address Harbour Point construction site, inspection photo 4, 2 September 2020

20 May 2020

28%+7.6 pts

  • Address Harbour Point construction site, inspection photo 1, 20 May 2020
  • Address Harbour Point construction site, inspection photo 2, 20 May 2020
  • Address Harbour Point construction site, inspection photo 3, 20 May 2020
  • Address Harbour Point construction site, inspection photo 4, 20 May 2020

All 159 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Address Harbour Point?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Address Harbour Point handover date?
Construction of Address Harbour Point is recorded as complete, with a registered completion date of January 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Address Harbour Point?
Address Harbour Point was 100% built at the site inspection on 12 January 2023. The site has been inspected 15 times since February 2018. The Land Department took 159 site photos at its inspections.
Is Address Harbour Point delayed?
The register lists construction as complete.
Who is building Address Harbour Point?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Address Harbour Point?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.