Address Harbour Point construction photos

159 photos from 15 site inspections, newest first. The percentage is how much of Address Harbour Point was built on the day of each visit.

12 January 2023100% built

19 September 202294% built

23 May 202290% built

29 December 202182% built

20 October 202175% built

13 July 202163% built

7 April 202152% built

30 December 202042% built

2 September 202033% built

20 May 202028% built

28 January 202020% built

27 October 201914% built

17 July 20198.4% built

26 June 20186.0% built

20 February 20182.3% built

Back to Address Harbour Point construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.