Vida Residence Downtown Dubai construction progress

The register lists Vida Residence Downtown Dubai in DownTown Dubai as complete, with a registered completion date of March 2019. Its last site inspection on record was in June 2019. The developer is Emaar Development.

100%

Built, at the site inspection of 13 June 2019

Construction complete

Registered completion date
March 2019
Construction started
January 2015
First registered
January 2014
Units
347
Escrow bank
Noor Bank
Name in Arabic
فيدا رزيدنس وسط مدينة دبي
Project number
1404
Site inspections
11

Schedule

The register lists Vida Residence Downtown Dubai as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 June 2019

100%+4.9 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 13 June 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 13 June 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 13 June 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 13 June 2019

21 February 2019

95%+14 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 21 February 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 21 February 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 21 February 2019
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 21 February 2019

30 October 2018

81%+5.7 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 30 October 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 30 October 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 30 October 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 30 October 2018

16 August 2018

75%+10 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 16 August 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 16 August 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 16 August 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 16 August 2018

28 May 2018

65%+23 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 28 May 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 28 May 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 28 May 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 28 May 2018

13 March 2018

42%+12 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 13 March 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 13 March 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 13 March 2018
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 13 March 2018

19 December 2017

31%+9.5 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 19 December 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 19 December 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 19 December 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 19 December 2017

2 August 2017

21%+10 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 2 August 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 2 August 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 2 August 2017
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 2 August 2017

22 June 2016

11%+3.4 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 22 June 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 22 June 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 22 June 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 22 June 2016

7 January 2016

7.7%+7.1 pts

  • Vida Residence Downtown Dubai construction site, inspection photo 1, 7 January 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 2, 7 January 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 3, 7 January 2016
  • Vida Residence Downtown Dubai construction site, inspection photo 4, 7 January 2016

All 102 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vida Residence Downtown Dubai?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vida Residence Downtown Dubai handover date?
Construction of Vida Residence Downtown Dubai is recorded as complete, with a registered completion date of March 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vida Residence Downtown Dubai?
Vida Residence Downtown Dubai was 100% built at the site inspection on 13 June 2019. The site has been inspected 11 times since March 2015. The Land Department took 102 site photos at its inspections.
Is Vida Residence Downtown Dubai delayed?
The register lists construction as complete.
Who is building Vida Residence Downtown Dubai?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Vida Residence Downtown Dubai?
Noor Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.