Opera Grand construction progress

The register lists Opera Grand in DownTown Dubai as complete, with a registered completion date of December 2021. Its last site inspection on record was in December 2021. The developer is Emaar Development.

100%

Built, at the site inspection of 9 December 2021

Construction complete

Registered completion date
December 2021
Construction started
June 2015
First registered
May 2014
Units
306
Escrow bank
Commercial Bank of Dubai
Name in Arabic
أوبرا جراند
Project number
1507
Site inspections
18

Schedule

The register lists Opera Grand as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 December 2021

100%+4.9 pts

  • Opera Grand construction site, inspection photo 1, 9 December 2021
  • Opera Grand construction site, inspection photo 2, 9 December 2021
  • Opera Grand construction site, inspection photo 3, 9 December 2021
  • Opera Grand construction site, inspection photo 4, 9 December 2021

12 September 2021

95%+3.5 pts

  • Opera Grand construction site, inspection photo 1, 12 September 2021
  • Opera Grand construction site, inspection photo 2, 12 September 2021
  • Opera Grand construction site, inspection photo 3, 12 September 2021
  • Opera Grand construction site, inspection photo 4, 12 September 2021

30 May 2021

92%+4.3 pts

  • Opera Grand construction site, inspection photo 1, 30 May 2021
  • Opera Grand construction site, inspection photo 2, 30 May 2021
  • Opera Grand construction site, inspection photo 3, 30 May 2021
  • Opera Grand construction site, inspection photo 4, 30 May 2021

25 January 2021

87%+4.9 pts

  • Opera Grand construction site, inspection photo 1, 25 January 2021
  • Opera Grand construction site, inspection photo 2, 25 January 2021
  • Opera Grand construction site, inspection photo 3, 25 January 2021
  • Opera Grand construction site, inspection photo 4, 25 January 2021

22 September 2020

82%+3.9 pts

  • Opera Grand construction site, inspection photo 1, 22 September 2020
  • Opera Grand construction site, inspection photo 2, 22 September 2020
  • Opera Grand construction site, inspection photo 3, 22 September 2020
  • Opera Grand construction site, inspection photo 4, 22 September 2020

8 June 2020

79%+3.5 pts

  • Opera Grand construction site, inspection photo 1, 8 June 2020
  • Opera Grand construction site, inspection photo 2, 8 June 2020
  • Opera Grand construction site, inspection photo 3, 8 June 2020
  • Opera Grand construction site, inspection photo 4, 8 June 2020

24 February 2020

75%+3.5 pts

  • Opera Grand construction site, inspection photo 1, 24 February 2020
  • Opera Grand construction site, inspection photo 2, 24 February 2020
  • Opera Grand construction site, inspection photo 3, 24 February 2020
  • Opera Grand construction site, inspection photo 4, 24 February 2020

14 November 2019

72%+4.4 pts

  • Opera Grand construction site, inspection photo 1, 14 November 2019
  • Opera Grand construction site, inspection photo 2, 14 November 2019
  • Opera Grand construction site, inspection photo 3, 14 November 2019
  • Opera Grand construction site, inspection photo 4, 14 November 2019

7 August 2019

67%+7.1 pts

  • Opera Grand construction site, inspection photo 1, 7 August 2019
  • Opera Grand construction site, inspection photo 2, 7 August 2019
  • Opera Grand construction site, inspection photo 3, 7 August 2019
  • Opera Grand construction site, inspection photo 4, 7 August 2019

25 April 2019

60%+12 pts

  • Opera Grand construction site, inspection photo 1, 25 April 2019
  • Opera Grand construction site, inspection photo 2, 25 April 2019
  • Opera Grand construction site, inspection photo 3, 25 April 2019
  • Opera Grand construction site, inspection photo 4, 25 April 2019

All 169 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Opera Grand?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Opera Grand handover date?
Construction of Opera Grand is recorded as complete, with a registered completion date of December 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Opera Grand?
Opera Grand was 100% built at the site inspection on 9 December 2021. The site has been inspected 18 times since April 2015. The Land Department took 169 site photos at its inspections.
Is Opera Grand delayed?
The register lists construction as complete.
Who is building Opera Grand?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Opera Grand?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.