Grande construction progress

The register lists Grande in DownTown Dubai as complete, with a registered completion date of June 2022. Its last site inspection on record was in May 2024. The developer is Emaar Development.

100%

Built, at the site inspection of 6 May 2024

Construction complete

Registered completion date
June 2022
Construction started
October 2017
First registered
April 2018
Units
912
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جراندي
Project number
2053
Site inspections
17

Schedule

The register lists Grande as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 May 2024

100%+6.3 pts

  • Grande construction site, inspection photo 1, 6 May 2024
  • Grande construction site, inspection photo 2, 6 May 2024
  • Grande construction site, inspection photo 3, 6 May 2024
  • Grande construction site, inspection photo 4, 6 May 2024

8 November 2023

94%+7.1 pts

  • Grande construction site, inspection photo 1, 8 November 2023
  • Grande construction site, inspection photo 2, 8 November 2023
  • Grande construction site, inspection photo 3, 8 November 2023
  • Grande construction site, inspection photo 4, 8 November 2023

18 July 2023

87%+6.2 pts

  • Grande construction site, inspection photo 1, 18 July 2023
  • Grande construction site, inspection photo 2, 18 July 2023
  • Grande construction site, inspection photo 3, 18 July 2023
  • Grande construction site, inspection photo 4, 18 July 2023

18 January 2023

80%+7.4 pts

  • Grande construction site, inspection photo 1, 18 January 2023
  • Grande construction site, inspection photo 2, 18 January 2023
  • Grande construction site, inspection photo 3, 18 January 2023
  • Grande construction site, inspection photo 4, 18 January 2023

12 September 2022

73%+4.9 pts

  • Grande construction site, inspection photo 1, 12 September 2022
  • Grande construction site, inspection photo 2, 12 September 2022
  • Grande construction site, inspection photo 3, 12 September 2022
  • Grande construction site, inspection photo 4, 12 September 2022

17 May 2022

68%+12 pts

  • Grande construction site, inspection photo 1, 17 May 2022
  • Grande construction site, inspection photo 2, 17 May 2022
  • Grande construction site, inspection photo 3, 17 May 2022
  • Grande construction site, inspection photo 4, 17 May 2022

25 November 2021

56%+7.9 pts

  • Grande construction site, inspection photo 1, 25 November 2021
  • Grande construction site, inspection photo 2, 25 November 2021
  • Grande construction site, inspection photo 3, 25 November 2021
  • Grande construction site, inspection photo 4, 25 November 2021

5 August 2021

48%+7.9 pts

  • Grande construction site, inspection photo 1, 5 August 2021
  • Grande construction site, inspection photo 2, 5 August 2021
  • Grande construction site, inspection photo 3, 5 August 2021
  • Grande construction site, inspection photo 4, 5 August 2021

13 April 2021

41%+10 pts

  • Grande construction site, inspection photo 1, 13 April 2021
  • Grande construction site, inspection photo 2, 13 April 2021
  • Grande construction site, inspection photo 3, 13 April 2021
  • Grande construction site, inspection photo 4, 13 April 2021

29 December 2020

30%+5.7 pts

  • Grande construction site, inspection photo 1, 29 December 2020
  • Grande construction site, inspection photo 2, 29 December 2020
  • Grande construction site, inspection photo 3, 29 December 2020
  • Grande construction site, inspection photo 4, 29 December 2020

All 154 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Grande?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Grande handover date?
Construction of Grande is recorded as complete, with a registered completion date of June 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Grande?
Grande was 100% built at the site inspection on 6 May 2024. The site has been inspected 17 times since October 2018. The Land Department took 154 site photos at its inspections.
Is Grande delayed?
The register lists construction as complete.
Who is building Grande?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Grande?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.