Burj Crown construction progress

The register lists Burj Crown in DownTown Dubai as complete, with a registered completion date of August 2023. Its last site inspection on record was in April 2023. The developer is Emaar Development.

100%

Built, at the site inspection of 12 April 2023

Construction complete

Registered completion date
August 2023
Construction started
May 2020
First registered
January 2020
Units
433
Escrow bank
Emirates NBD
Name in Arabic
برج كراون
Project number
2201
Site inspections
9

Schedule

The register lists Burj Crown as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 April 2023

92%+11 pts

  • Burj Crown construction site, inspection photo 1, 12 April 2023
  • Burj Crown construction site, inspection photo 2, 12 April 2023
  • Burj Crown construction site, inspection photo 3, 12 April 2023
  • Burj Crown construction site, inspection photo 4, 12 April 2023

28 December 2022

81%+18 pts

  • Burj Crown construction site, inspection photo 1, 28 December 2022
  • Burj Crown construction site, inspection photo 2, 28 December 2022
  • Burj Crown construction site, inspection photo 3, 28 December 2022
  • Burj Crown construction site, inspection photo 4, 28 December 2022

9 September 2022

63%+20 pts

  • Burj Crown construction site, inspection photo 1, 9 September 2022
  • Burj Crown construction site, inspection photo 2, 9 September 2022
  • Burj Crown construction site, inspection photo 3, 9 September 2022
  • Burj Crown construction site, inspection photo 4, 9 September 2022

25 May 2022

43%+17 pts

  • Burj Crown construction site, inspection photo 1, 25 May 2022
  • Burj Crown construction site, inspection photo 2, 25 May 2022
  • Burj Crown construction site, inspection photo 3, 25 May 2022
  • Burj Crown construction site, inspection photo 4, 25 May 2022

14 January 2022

26%+5.9 pts

  • Burj Crown construction site, inspection photo 1, 14 January 2022
  • Burj Crown construction site, inspection photo 2, 14 January 2022
  • Burj Crown construction site, inspection photo 3, 14 January 2022
  • Burj Crown construction site, inspection photo 4, 14 January 2022

29 September 2021

20%+9.7 pts

  • Burj Crown construction site, inspection photo 1, 29 September 2021
  • Burj Crown construction site, inspection photo 2, 29 September 2021
  • Burj Crown construction site, inspection photo 3, 29 September 2021
  • Burj Crown construction site, inspection photo 4, 29 September 2021

15 June 2021

10%+4.6 pts

  • Burj Crown construction site, inspection photo 1, 15 June 2021
  • Burj Crown construction site, inspection photo 2, 15 June 2021
  • Burj Crown construction site, inspection photo 3, 15 June 2021
  • Burj Crown construction site, inspection photo 4, 15 June 2021

16 December 2020

5.8%+3.5 pts

  • Burj Crown construction site, inspection photo 1, 16 December 2020
  • Burj Crown construction site, inspection photo 2, 16 December 2020
  • Burj Crown construction site, inspection photo 3, 16 December 2020
  • Burj Crown construction site, inspection photo 4, 16 December 2020

26 August 2020

2.3%

  • Burj Crown construction site, inspection photo 1, 26 August 2020
  • Burj Crown construction site, inspection photo 2, 26 August 2020
  • Burj Crown construction site, inspection photo 3, 26 August 2020
  • Burj Crown construction site, inspection photo 4, 26 August 2020

All 80 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Burj Crown?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Burj Crown handover date?
Construction of Burj Crown is recorded as complete, with a registered completion date of August 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Burj Crown?
Burj Crown was 100% built at the site inspection on 12 April 2023. The site has been inspected 9 times since August 2020. The Land Department took 80 site photos at its inspections.
Is Burj Crown delayed?
The register lists construction as complete.
Who is building Burj Crown?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Burj Crown?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.