Address Grand Downtown construction progress
Address Grand Downtown in Downtown Dubai is 4.7% built at the Land Department inspection of April 2026. Developer Nshama Properties. Completion registered for June 2028.
11%
Built, at the Land Department site inspection of 30 April 2026
Running behind its date
- Completion date (Land Department)
- June 2028
- Finish at recent pace
- December 2032
- Construction started
- June 2025
- Registered with the Land Department
- February 2025
- Developer
- Nshama Properties
- Community
- Downtown Dubai
- Units
- 80
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- العنوان جراند داون تاون
- Land Department project number
- 3487
- Land Department site inspections
- 3
Schedule
Between January 2026 and April 2026 the site added about 1.2 points a month. At that rate it would finish around December 2032, more than three months after the June 2028 date registered with the Land Department.
Site inspections
30 April 2026
4.7%+4.3 pts
9 January 2026
0.4%+0.4 pts
16 January 2025
0%
Context
Downtown Dubai has 13 projects under construction, 33% built on average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Address Grand Downtown?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Address Grand Downtown be completed?
- The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around December 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Address Grand Downtown is built?
- 11%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is Address Grand Downtown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Address Grand Downtown?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Address Grand Downtown?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SymphonyAlso by Nshama Properties. 73%.
- GroveAlso by Nshama Properties. 41%.
- ElayaAlso by Nshama Properties. 52%.
- FiaAlso by Nshama Properties. 85%.
- The St. Regis Residences, Downtown DubaiNearby in Downtown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in Downtown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in Downtown Dubai. 65%, Due December 2026.
- Baccarat Hotel And Residences, DubaiNearby in Downtown Dubai. 21%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.







.jpeg&w=3840&q=75)