Symphony construction progress

Symphony in Town Square is 73% built at the Land Department inspection of April 2026. Developer Nshama Properties.

73%

Built, at the Land Department site inspection of 30 April 2026

Finish at recent pace
November 2026
Construction started
February 2024
Registered with the Land Department
September 2023
Community
Town Square
Units
398
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سيمفوني
Land Department project number
2786
Land Department site inspections
6

Schedule

Since July 2025 Symphony has added about 3.8 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

30 April 2026

73%+16 pts

  • Symphony construction site, Land Department inspection photo 1, 30 April 2026
  • Symphony construction site, Land Department inspection photo 2, 30 April 2026
  • Symphony construction site, Land Department inspection photo 3, 30 April 2026
  • Symphony construction site, Land Department inspection photo 4, 30 April 2026

15 December 2025

57%+21 pts

  • Symphony construction site, Land Department inspection photo 1, 15 December 2025
  • Symphony construction site, Land Department inspection photo 2, 15 December 2025
  • Symphony construction site, Land Department inspection photo 3, 15 December 2025
  • Symphony construction site, Land Department inspection photo 4, 15 December 2025

3 July 2025

36%+20 pts

  • Symphony construction site, Land Department inspection photo 1, 3 July 2025
  • Symphony construction site, Land Department inspection photo 2, 3 July 2025
  • Symphony construction site, Land Department inspection photo 3, 3 July 2025
  • Symphony construction site, Land Department inspection photo 4, 3 July 2025

24 February 2025

16%+8.5 pts

  • Symphony construction site, Land Department inspection photo 1, 24 February 2025
  • Symphony construction site, Land Department inspection photo 2, 24 February 2025
  • Symphony construction site, Land Department inspection photo 3, 24 February 2025
  • Symphony construction site, Land Department inspection photo 4, 24 February 2025

12 December 2024

7.4%+7.4 pts

  • Symphony construction site, Land Department inspection photo 1, 12 December 2024
  • Symphony construction site, Land Department inspection photo 2, 12 December 2024
  • Symphony construction site, Land Department inspection photo 3, 12 December 2024

19 September 2023

0%

  • Symphony construction site, Land Department inspection photo 1, 19 September 2023
  • Symphony construction site, Land Department inspection photo 2, 19 September 2023
  • Symphony construction site, Land Department inspection photo 3, 19 September 2023

All 36 site photos, by inspection date

Context

Town Square has 19 projects under construction, 30% built on average. Symphony is ahead of that average.

Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Symphony?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Symphony be completed?
The Land Department has no completion date on record for Symphony yet. It appears once the developer registers the construction timeline.
How much of Symphony is built?
73%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 6 times since September 2023.
Who is building Symphony?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Symphony?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.