Symphony construction progress
Symphony in Town Square is 73% built at the Land Department inspection of April 2026. Developer Nshama Properties.
73%
Built, at the Land Department site inspection of 30 April 2026
- Finish at recent pace
- November 2026
- Construction started
- February 2024
- Registered with the Land Department
- September 2023
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 398
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سيمفوني
- Land Department project number
- 2786
- Land Department site inspections
- 6
Schedule
Since July 2025 Symphony has added about 3.8 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.
Site inspections
30 April 2026
73%+16 pts
15 December 2025
57%+21 pts
3 July 2025
36%+20 pts
24 February 2025
16%+8.5 pts
12 December 2024
7.4%+7.4 pts
19 September 2023
0%
Context
Town Square has 19 projects under construction, 30% built on average. Symphony is ahead of that average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Symphony?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Symphony be completed?
- The Land Department has no completion date on record for Symphony yet. It appears once the developer registers the construction timeline.
- How much of Symphony is built?
- 73%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 6 times since September 2023.
- Who is building Symphony?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Symphony?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)