Fia construction progress

Fia in Town Square is 85% built at the Land Department inspection of September 2026. Developer Nshama Properties.

85%

Built, at the Land Department site inspection of 17 September 2026

Finish at recent pace
December 2026
Construction started
September 2024
Registered with the Land Department
March 2024
Community
Town Square
Units
192
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيا
Land Department project number
3000
Land Department site inspections
7

Schedule

Since September 2025 Fia has added about 5.3 points a month. At that rate the site reaches 100% around December 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

17 September 2026

85%+37 pts

  • Fia construction site, Land Department inspection photo 1, 17 September 2026
  • Fia construction site, Land Department inspection photo 2, 17 September 2026
  • Fia construction site, Land Department inspection photo 3, 17 September 2026
  • Fia construction site, Land Department inspection photo 4, 17 September 2026

30 April 2026

48%+13 pts

  • Fia construction site, Land Department inspection photo 1, 30 April 2026
  • Fia construction site, Land Department inspection photo 2, 30 April 2026
  • Fia construction site, Land Department inspection photo 3, 30 April 2026
  • Fia construction site, Land Department inspection photo 4, 30 April 2026

9 January 2026

34%+13 pts

  • Fia construction site, Land Department inspection photo 1, 9 January 2026
  • Fia construction site, Land Department inspection photo 2, 9 January 2026
  • Fia construction site, Land Department inspection photo 3, 9 January 2026
  • Fia construction site, Land Department inspection photo 4, 9 January 2026

19 September 2025

21%+10 pts

  • Fia construction site, Land Department inspection photo 1, 19 September 2025
  • Fia construction site, Land Department inspection photo 2, 19 September 2025
  • Fia construction site, Land Department inspection photo 3, 19 September 2025
  • Fia construction site, Land Department inspection photo 4, 19 September 2025

24 April 2025

11%+6.9 pts

  • Fia construction site, Land Department inspection photo 1, 24 April 2025
  • Fia construction site, Land Department inspection photo 2, 24 April 2025
  • Fia construction site, Land Department inspection photo 3, 24 April 2025
  • Fia construction site, Land Department inspection photo 4, 24 April 2025

24 January 2025

3.6%+3.6 pts

  • Fia construction site, Land Department inspection photo 1, 24 January 2025
  • Fia construction site, Land Department inspection photo 2, 24 January 2025
  • Fia construction site, Land Department inspection photo 3, 24 January 2025
  • Fia construction site, Land Department inspection photo 4, 24 January 2025

8 March 2024

0%

  • Fia construction site, Land Department inspection photo 1, 8 March 2024
  • Fia construction site, Land Department inspection photo 2, 8 March 2024
  • Fia construction site, Land Department inspection photo 3, 8 March 2024

All 41 site photos, by inspection date

Context

Town Square has 19 projects under construction, 30% built on average. Fia is ahead of that average.

Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Fia?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Fia be completed?
The Land Department has no completion date on record for Fia yet. It appears once the developer registers the construction timeline.
How much of Fia is built?
85%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 7 times since March 2024.
Who is building Fia?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Fia?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.