Grove construction progress
Grove in Town Square is 41% built at the Land Department inspection of September 2026. Developer Nshama Properties.
41%
Built, at the Land Department site inspection of 15 September 2026
- Finish at recent pace
- January 2028
- Construction started
- May 2024
- Registered with the Land Department
- December 2023
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 378
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- جروف
- Land Department project number
- 2850
- Land Department site inspections
- 6
Schedule
Since January 2026 Grove has added about 3.8 points a month. At that rate the site reaches 100% around January 2028. The Land Department has no completion date on record to compare it with.
Site inspections
15 September 2026
41%+25 pts
30 April 2026
16%+5.8 pts
9 January 2026
9.7%+9.2 pts
8 April 2025
0.5%+0.4 pts
12 December 2024
0.1%+0.1 pts
12 December 2023
0%
Context
Town Square has 19 projects under construction, 30% built on average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Grove?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Grove be completed?
- The Land Department has no completion date on record for Grove yet.
- How much of Grove is built?
- 41%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 6 times since December 2023.
- Who is building Grove?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Grove?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)