Act One | Act Two construction progress

The register lists Act One | Act Two in DownTown Dubai as complete, with a registered completion date of December 2022. Its last site inspection on record was in December 2022. The developer is Emaar Development.

100%

Built, at the site inspection of 26 December 2022

Construction complete

Registered completion date
December 2022
Construction started
February 2017
First registered
August 2016
Units
788
Escrow bank
Emirates NBD
Name in Arabic
Act ون | Act تو
Project number
1773
Site inspections
19

Schedule

The register lists Act One | Act Two as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 December 2022

100%+8.4 pts

  • Act One | Act Two construction site, inspection photo 1, 26 December 2022
  • Act One | Act Two construction site, inspection photo 2, 26 December 2022
  • Act One | Act Two construction site, inspection photo 3, 26 December 2022
  • Act One | Act Two construction site, inspection photo 4, 26 December 2022

31 August 2022

92%+3.7 pts

  • Act One | Act Two construction site, inspection photo 1, 31 August 2022
  • Act One | Act Two construction site, inspection photo 2, 31 August 2022
  • Act One | Act Two construction site, inspection photo 3, 31 August 2022
  • Act One | Act Two construction site, inspection photo 4, 31 August 2022

11 May 2022

88%+6.1 pts

  • Act One | Act Two construction site, inspection photo 1, 11 May 2022
  • Act One | Act Two construction site, inspection photo 2, 11 May 2022
  • Act One | Act Two construction site, inspection photo 3, 11 May 2022
  • Act One | Act Two construction site, inspection photo 4, 11 May 2022

29 December 2021

82%+7.3 pts

  • Act One | Act Two construction site, inspection photo 1, 29 December 2021
  • Act One | Act Two construction site, inspection photo 2, 29 December 2021
  • Act One | Act Two construction site, inspection photo 3, 29 December 2021
  • Act One | Act Two construction site, inspection photo 4, 29 December 2021

16 September 2021

74%+4.2 pts

  • Act One | Act Two construction site, inspection photo 1, 16 September 2021
  • Act One | Act Two construction site, inspection photo 2, 16 September 2021
  • Act One | Act Two construction site, inspection photo 3, 16 September 2021
  • Act One | Act Two construction site, inspection photo 4, 16 September 2021

6 June 2021

70%+10 pts

  • Act One | Act Two construction site, inspection photo 1, 6 June 2021
  • Act One | Act Two construction site, inspection photo 2, 6 June 2021
  • Act One | Act Two construction site, inspection photo 3, 6 June 2021
  • Act One | Act Two construction site, inspection photo 4, 6 June 2021

25 January 2021

60%+7.1 pts

  • Act One | Act Two construction site, inspection photo 1, 25 January 2021
  • Act One | Act Two construction site, inspection photo 2, 25 January 2021
  • Act One | Act Two construction site, inspection photo 3, 25 January 2021
  • Act One | Act Two construction site, inspection photo 4, 25 January 2021

22 October 2020

53%+5.0 pts

  • Act One | Act Two construction site, inspection photo 1, 22 October 2020
  • Act One | Act Two construction site, inspection photo 2, 22 October 2020
  • Act One | Act Two construction site, inspection photo 3, 22 October 2020
  • Act One | Act Two construction site, inspection photo 4, 22 October 2020

9 July 2020

48%+3.9 pts

  • Act One | Act Two construction site, inspection photo 1, 9 July 2020
  • Act One | Act Two construction site, inspection photo 2, 9 July 2020
  • Act One | Act Two construction site, inspection photo 3, 9 July 2020
  • Act One | Act Two construction site, inspection photo 4, 9 July 2020

30 March 2020

44%+8.1 pts

  • Act One | Act Two construction site, inspection photo 1, 30 March 2020
  • Act One | Act Two construction site, inspection photo 2, 30 March 2020
  • Act One | Act Two construction site, inspection photo 3, 30 March 2020
  • Act One | Act Two construction site, inspection photo 4, 30 March 2020

All 162 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Act One | Act Two?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Act One | Act Two handover date?
Construction of Act One | Act Two is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Act One | Act Two?
Act One | Act Two was 100% built at the site inspection on 26 December 2022. The site has been inspected 19 times since March 2017. The Land Department took 162 site photos at its inspections.
Is Act One | Act Two delayed?
The register lists construction as complete.
Who is building Act One | Act Two?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Act One | Act Two?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.