Azizi Aura Residences construction progress

The register lists Azizi Aura Residences in Down Town Jabal Ali as complete, with a registered completion date of May 2020. Its last site inspection on record was in December 2020. The developer is Azizi Developments.

100%

Built, at the site inspection of 20 December 2020

Construction complete

Registered completion date
May 2020
Construction started
May 2017
First registered
April 2017
Units
487
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي أورا ريزيدنزس
Project number
1897
Site inspections
6

Schedule

The register lists Azizi Aura Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 December 2020

100%+25 pts

  • Azizi Aura Residences construction site, inspection photo 1, 20 December 2020
  • Azizi Aura Residences construction site, inspection photo 2, 20 December 2020
  • Azizi Aura Residences construction site, inspection photo 3, 20 December 2020
  • Azizi Aura Residences construction site, inspection photo 4, 20 December 2020

19 February 2020

75%+17 pts

  • Azizi Aura Residences construction site, inspection photo 1, 19 February 2020
  • Azizi Aura Residences construction site, inspection photo 2, 19 February 2020
  • Azizi Aura Residences construction site, inspection photo 3, 19 February 2020
  • Azizi Aura Residences construction site, inspection photo 4, 19 February 2020

12 September 2019

58%+21 pts

  • Azizi Aura Residences construction site, inspection photo 1, 12 September 2019
  • Azizi Aura Residences construction site, inspection photo 2, 12 September 2019
  • Azizi Aura Residences construction site, inspection photo 3, 12 September 2019
  • Azizi Aura Residences construction site, inspection photo 4, 12 September 2019

16 April 2019

37%+17 pts

  • Azizi Aura Residences construction site, inspection photo 1, 16 April 2019
  • Azizi Aura Residences construction site, inspection photo 2, 16 April 2019
  • Azizi Aura Residences construction site, inspection photo 3, 16 April 2019
  • Azizi Aura Residences construction site, inspection photo 4, 16 April 2019

14 October 2018

20%+16 pts

  • Azizi Aura Residences construction site, inspection photo 1, 14 October 2018
  • Azizi Aura Residences construction site, inspection photo 2, 14 October 2018
  • Azizi Aura Residences construction site, inspection photo 3, 14 October 2018
  • Azizi Aura Residences construction site, inspection photo 4, 14 October 2018

28 March 2018

4.5%

  • Azizi Aura Residences construction site, inspection photo 1, 28 March 2018
  • Azizi Aura Residences construction site, inspection photo 2, 28 March 2018
  • Azizi Aura Residences construction site, inspection photo 3, 28 March 2018
  • Azizi Aura Residences construction site, inspection photo 4, 28 March 2018

All 56 site photos, by inspection date

Context

Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Aura Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Aura Residences handover date?
Construction of Azizi Aura Residences is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Aura Residences?
Azizi Aura Residences was 100% built at the site inspection on 20 December 2020. The site has been inspected 6 times since March 2018. The Land Department took 56 site photos at its inspections.
Is Azizi Aura Residences delayed?
The register lists construction as complete.
Who is building Azizi Aura Residences?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Aura Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.