Azizi Aura Residences construction photos

56 photos from 6 site inspections, newest first. The percentage is how much of Azizi Aura Residences was built on the day of each visit.

20 December 2020100% built

19 February 202075% built

12 September 201958% built

16 April 201937% built

14 October 201820% built

28 March 20184.5% built

Back to Azizi Aura Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.