West Bay Tower construction photos

154 photos from 23 site inspections, newest first. The percentage is how much of West Bay Tower was built on the day of each visit.

20 April 202683% built

28 January 202678% built

11 September 202577% built

11 April 202562% built

11 November 202457% built

13 February 202448% built

1 August 202339% built

17 March 202334% built

24 November 202230% built

20 July 202227% built

19 September 202125% built

31 May 202122% built

27 December 202021% built

14 October 202019% built

27 May 202014% built

27 November 201910% built

14 July 20199.6% built

21 January 20199.2% built

18 July 20188.0% built

9 April 20183.6% built

29 January 20181.4% built

19 November 20171.1% built

20 October 20160.1% built

Back to West Bay Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.