Vyb construction progress

The register lists Vyb in Business Bay as complete, with a registered completion date of February 2026. Its last site inspection on record was in June 2026. The developer is Ginco Properties.

100%

Built, at the site inspection of 16 June 2026

Construction complete

Registered completion date
February 2026
Construction started
August 2023
First registered
August 2023
Community
Business Bay
Units
181
Escrow bank
Emirates Islamic Bank
Name in Arabic
فايب
Project number
2727
Site inspections
7

Schedule

The register lists Vyb as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 June 2026

100%+1.9 pts

  • Vyb construction site, inspection photo 1, 16 June 2026
  • Vyb construction site, inspection photo 2, 16 June 2026
  • Vyb construction site, inspection photo 3, 16 June 2026
  • Vyb construction site, inspection photo 4, 16 June 2026

9 February 2026

98%+30 pts

  • Vyb construction site, inspection photo 1, 9 February 2026
  • Vyb construction site, inspection photo 2, 9 February 2026
  • Vyb construction site, inspection photo 3, 9 February 2026
  • Vyb construction site, inspection photo 4, 9 February 2026

3 October 2025

68%+20 pts

  • Vyb construction site, inspection photo 1, 3 October 2025
  • Vyb construction site, inspection photo 2, 3 October 2025
  • Vyb construction site, inspection photo 3, 3 October 2025
  • Vyb construction site, inspection photo 4, 3 October 2025

18 April 2025

48%+20 pts

  • Vyb construction site, inspection photo 1, 18 April 2025
  • Vyb construction site, inspection photo 2, 18 April 2025
  • Vyb construction site, inspection photo 3, 18 April 2025
  • Vyb construction site, inspection photo 4, 18 April 2025

10 December 2024

28%+15 pts

  • Vyb construction site, inspection photo 1, 10 December 2024
  • Vyb construction site, inspection photo 2, 10 December 2024
  • Vyb construction site, inspection photo 3, 10 December 2024
  • Vyb construction site, inspection photo 4, 10 December 2024

28 May 2024

14%+14 pts

  • Vyb construction site, inspection photo 1, 28 May 2024
  • Vyb construction site, inspection photo 2, 28 May 2024
  • Vyb construction site, inspection photo 3, 28 May 2024
  • Vyb construction site, inspection photo 4, 28 May 2024

26 July 2023

0%

  • Vyb construction site, inspection photo 1, 26 July 2023
  • Vyb construction site, inspection photo 2, 26 July 2023
  • Vyb construction site, inspection photo 3, 26 July 2023

All 54 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Ginco Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vyb?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vyb handover date?
Construction of Vyb is recorded as complete, with a registered completion date of February 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vyb?
Vyb was 100% built at the site inspection on 16 June 2026. The site has been inspected 7 times since July 2023. The Land Department took 54 site photos at its inspections.
Is Vyb delayed?
The register lists construction as complete.
Who is building Vyb?
The registered developer is Ginco Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Vyb?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.