One Residence construction progress

One Residence in DownTown Dubai is 6.3% built at the Land Department inspection of July 2026. Developer Ginco Properties. Completion registered for March 2027.

6.3%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
July 2060
Construction started
October 2024
Registered with the Land Department
July 2024
Developer
Ginco Properties
Units
458
Escrow bank
Emirates Islamic Bank
Name in Arabic
وان ريزيدنس
Land Department project number
3150
Land Department site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around July 2060, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

6.3%+0.3 pts

  • One Residence construction site, Land Department inspection photo 1, 27 July 2026
  • One Residence construction site, Land Department inspection photo 2, 27 July 2026
  • One Residence construction site, Land Department inspection photo 3, 27 July 2026
  • One Residence construction site, Land Department inspection photo 4, 27 July 2026

9 February 2026

6.0%+1.7 pts

  • One Residence construction site, Land Department inspection photo 1, 9 February 2026
  • One Residence construction site, Land Department inspection photo 2, 9 February 2026
  • One Residence construction site, Land Department inspection photo 3, 9 February 2026
  • One Residence construction site, Land Department inspection photo 4, 9 February 2026

27 October 2025

4.3%+2.9 pts

  • One Residence construction site, Land Department inspection photo 1, 27 October 2025
  • One Residence construction site, Land Department inspection photo 2, 27 October 2025
  • One Residence construction site, Land Department inspection photo 3, 27 October 2025

19 May 2025

1.3%+1.3 pts

  • One Residence construction site, Land Department inspection photo 1, 19 May 2025
  • One Residence construction site, Land Department inspection photo 2, 19 May 2025
  • One Residence construction site, Land Department inspection photo 3, 19 May 2025
  • One Residence construction site, Land Department inspection photo 4, 19 May 2025

21 June 2024

0%

  • One Residence construction site, Land Department inspection photo 1, 21 June 2024
  • One Residence construction site, Land Department inspection photo 2, 21 June 2024
  • One Residence construction site, Land Department inspection photo 3, 21 June 2024
  • One Residence construction site, Land Department inspection photo 4, 21 June 2024

All 22 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 33% built on average.

Ginco Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in One Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will One Residence be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around July 2060. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of One Residence is built?
6.3%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is One Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building One Residence?
The registered developer is Ginco Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for One Residence?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.