One Residence construction progress

The registered completion date for One Residence in DownTown Dubai is March 2027. At the last site inspection, in July 2026, it was 6.3% built. The developer is Ginco Properties.

8.0%

Built, at the site inspection of 27 July 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
July 2060
Construction started
October 2024
First registered
July 2024
Developer
Ginco Properties
Units
458
Escrow bank
Emirates Islamic Bank
Name in Arabic
وان ريزيدنس
Project number
3150
Site inspections
5

Schedule

Between October 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around July 2060, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

6.3%+0.3 pts

  • One Residence construction site, inspection photo 1, 27 July 2026
  • One Residence construction site, inspection photo 2, 27 July 2026
  • One Residence construction site, inspection photo 3, 27 July 2026
  • One Residence construction site, inspection photo 4, 27 July 2026

9 February 2026

6.0%+1.7 pts

  • One Residence construction site, inspection photo 1, 9 February 2026
  • One Residence construction site, inspection photo 2, 9 February 2026
  • One Residence construction site, inspection photo 3, 9 February 2026
  • One Residence construction site, inspection photo 4, 9 February 2026

27 October 2025

4.3%+2.9 pts

  • One Residence construction site, inspection photo 1, 27 October 2025
  • One Residence construction site, inspection photo 2, 27 October 2025
  • One Residence construction site, inspection photo 3, 27 October 2025

19 May 2025

1.3%+1.3 pts

  • One Residence construction site, inspection photo 1, 19 May 2025
  • One Residence construction site, inspection photo 2, 19 May 2025
  • One Residence construction site, inspection photo 3, 19 May 2025
  • One Residence construction site, inspection photo 4, 19 May 2025

21 June 2024

0%

  • One Residence construction site, inspection photo 1, 21 June 2024
  • One Residence construction site, inspection photo 2, 21 June 2024
  • One Residence construction site, inspection photo 3, 21 June 2024
  • One Residence construction site, inspection photo 4, 21 June 2024

All 22 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Ginco Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in One Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the One Residence handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2060. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on One Residence?
One Residence was 8.0% built at the site inspection on 27 July 2026. The site has been inspected 5 times since June 2024. The Land Department took 22 site photos at its inspections.
Is One Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building One Residence?
The registered developer is Ginco Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for One Residence?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.