Vela Viento By Omniyat construction photos

33 photos from 7 site inspections, newest first. The percentage is how much of Vela Viento By Omniyat was built on the day of each visit.

18 May 202622% built

16 February 202618% built

3 November 202514% built

4 July 20258.8% built

9 May 20257.3% built

17 March 20256.3% built

27 February 20240% built

Back to Vela Viento By Omniyat construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.