The Paragon By Igo construction progress

The register lists The Paragon By Igo in Business Bay as complete, with a registered completion date of May 2025. Its last site inspection on record was in May 2025. The developer is Igo Real Estate Development.

100%

Built, at the site inspection of 13 May 2025

Construction complete

Registered completion date
May 2025
Construction started
June 2022
First registered
June 2022
Developer
Igo Real Estate Development
Community
Business Bay
Units
330
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذي باراغون باي أي جي أو
Project number
2402
Site inspections
7

Schedule

The register lists The Paragon By Igo as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 May 2025

100%+34 pts

  • The Paragon By Igo construction site, inspection photo 1, 13 May 2025
  • The Paragon By Igo construction site, inspection photo 2, 13 May 2025
  • The Paragon By Igo construction site, inspection photo 3, 13 May 2025
  • The Paragon By Igo construction site, inspection photo 4, 13 May 2025

18 September 2024

66%+13 pts

  • The Paragon By Igo construction site, inspection photo 1, 18 September 2024
  • The Paragon By Igo construction site, inspection photo 2, 18 September 2024
  • The Paragon By Igo construction site, inspection photo 3, 18 September 2024
  • The Paragon By Igo construction site, inspection photo 4, 18 September 2024

5 June 2024

53%+21 pts

  • The Paragon By Igo construction site, inspection photo 1, 5 June 2024
  • The Paragon By Igo construction site, inspection photo 2, 5 June 2024
  • The Paragon By Igo construction site, inspection photo 3, 5 June 2024
  • The Paragon By Igo construction site, inspection photo 4, 5 June 2024

14 February 2024

32%+11 pts

  • The Paragon By Igo construction site, inspection photo 1, 14 February 2024
  • The Paragon By Igo construction site, inspection photo 2, 14 February 2024
  • The Paragon By Igo construction site, inspection photo 3, 14 February 2024
  • The Paragon By Igo construction site, inspection photo 4, 14 February 2024

2 October 2023

21%+6.4 pts

  • The Paragon By Igo construction site, inspection photo 1, 2 October 2023
  • The Paragon By Igo construction site, inspection photo 2, 2 October 2023
  • The Paragon By Igo construction site, inspection photo 3, 2 October 2023
  • The Paragon By Igo construction site, inspection photo 4, 2 October 2023

4 July 2023

15%+5.2 pts

  • The Paragon By Igo construction site, inspection photo 1, 4 July 2023
  • The Paragon By Igo construction site, inspection photo 2, 4 July 2023
  • The Paragon By Igo construction site, inspection photo 3, 4 July 2023
  • The Paragon By Igo construction site, inspection photo 4, 4 July 2023

9 February 2023

9.3%

  • The Paragon By Igo construction site, inspection photo 1, 9 February 2023
  • The Paragon By Igo construction site, inspection photo 2, 9 February 2023
  • The Paragon By Igo construction site, inspection photo 3, 9 February 2023
  • The Paragon By Igo construction site, inspection photo 4, 9 February 2023

All 61 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in The Paragon By Igo?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Paragon By Igo handover date?
Construction of The Paragon By Igo is recorded as complete, with a registered completion date of May 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Paragon By Igo?
The Paragon By Igo was 100% built at the site inspection on 13 May 2025. The site has been inspected 7 times since February 2023. The Land Department took 61 site photos at its inspections.
Is The Paragon By Igo delayed?
The register lists construction as complete.
Who is building The Paragon By Igo?
The registered developer is Igo Real Estate Development.
Which bank holds the escrow account for The Paragon By Igo?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.