The Paragon By Igo construction photos

61 photos from 7 site inspections, newest first. The percentage is how much of The Paragon By Igo was built on the day of each visit.

13 May 2025100% built

18 September 202466% built

5 June 202453% built

14 February 202432% built

2 October 202321% built

4 July 202315% built

9 February 20239.3% built

Back to The Paragon By Igo construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.