The Pad construction progress

The register lists The Pad in Business Bay as complete, with a registered completion date of October 2020. Its last site inspection on record was in October 2020. The developer is Pad Properties Nine Limited.

100%

Built, at the site inspection of 14 October 2020

Construction complete

Registered completion date
October 2020
Construction started
December 2008
First registered
September 2007
Developer
Pad Properties Nine Limited
Community
Business Bay
Units
265
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا باد
Project number
1173
Site inspections
15

Schedule

The register lists The Pad as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201220152018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 October 2020

100%+2.0 pts

  • The Pad construction site, inspection photo 1, 14 October 2020
  • The Pad construction site, inspection photo 2, 14 October 2020
  • The Pad construction site, inspection photo 3, 14 October 2020
  • The Pad construction site, inspection photo 4, 14 October 2020

17 May 2020

98%+3.6 pts

  • The Pad construction site, inspection photo 1, 17 May 2020
  • The Pad construction site, inspection photo 2, 17 May 2020
  • The Pad construction site, inspection photo 3, 17 May 2020
  • The Pad construction site, inspection photo 4, 17 May 2020

25 June 2019

94%+3.7 pts

  • The Pad construction site, inspection photo 1, 25 June 2019
  • The Pad construction site, inspection photo 2, 25 June 2019
  • The Pad construction site, inspection photo 3, 25 June 2019
  • The Pad construction site, inspection photo 4, 25 June 2019

29 October 2018

91%+0.4 pts

  • The Pad construction site, inspection photo 1, 29 October 2018
  • The Pad construction site, inspection photo 2, 29 October 2018
  • The Pad construction site, inspection photo 3, 29 October 2018
  • The Pad construction site, inspection photo 4, 29 October 2018

5 November 2017

90%+4.2 pts

  • The Pad construction site, inspection photo 1, 5 November 2017
  • The Pad construction site, inspection photo 2, 5 November 2017
  • The Pad construction site, inspection photo 3, 5 November 2017
  • The Pad construction site, inspection photo 4, 5 November 2017

23 May 2017

86%+5.2 pts

  • The Pad construction site, inspection photo 1, 23 May 2017
  • The Pad construction site, inspection photo 2, 23 May 2017
  • The Pad construction site, inspection photo 3, 23 May 2017
  • The Pad construction site, inspection photo 4, 23 May 2017

12 December 2016

81%+6.3 pts

  • The Pad construction site, inspection photo 1, 12 December 2016
  • The Pad construction site, inspection photo 2, 12 December 2016
  • The Pad construction site, inspection photo 3, 12 December 2016
  • The Pad construction site, inspection photo 4, 12 December 2016

2 May 2016

75%+8.5 pts

  • The Pad construction site, inspection photo 1, 2 May 2016
  • The Pad construction site, inspection photo 2, 2 May 2016
  • The Pad construction site, inspection photo 3, 2 May 2016
  • The Pad construction site, inspection photo 4, 2 May 2016

23 December 2015

66%+10 pts

  • The Pad construction site, inspection photo 1, 23 December 2015
  • The Pad construction site, inspection photo 2, 23 December 2015
  • The Pad construction site, inspection photo 3, 23 December 2015
  • The Pad construction site, inspection photo 4, 23 December 2015

9 July 2015

56%+5.9 pts

  • The Pad construction site, inspection photo 1, 9 July 2015
  • The Pad construction site, inspection photo 2, 9 July 2015
  • The Pad construction site, inspection photo 3, 9 July 2015
  • The Pad construction site, inspection photo 4, 9 July 2015

All 142 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in The Pad?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Pad handover date?
Construction of The Pad is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Pad?
The Pad was 100% built at the site inspection on 14 October 2020. The site has been inspected 15 times since September 2013. The Land Department took 142 site photos at its inspections.
Is The Pad delayed?
The register lists construction as complete.
Who is building The Pad?
The registered developer is Pad Properties Nine Limited.
Which bank holds the escrow account for The Pad?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.