142 photos from 15 site inspections, newest first. The percentage is how much of The Pad was built on the day of each visit.

14 October 2020100% built

17 May 202098% built

25 June 201994% built

29 October 201891% built

5 November 201790% built

23 May 201786% built

12 December 201681% built

2 May 201675% built

23 December 201566% built

9 July 201556% built

15 February 201550% built

18 December 201441% built

12 July 201432% built

21 January 201425% built

3 September 201325% built

Back to The Pad construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.