The Pad construction photos
142 photos from 15 site inspections, newest first. The percentage is how much of The Pad was built on the day of each visit.
14 October 2020100% built
17 May 202098% built
25 June 201994% built
29 October 201891% built
5 November 201790% built
23 May 201786% built
12 December 201681% built
2 May 201675% built
23 December 201566% built
9 July 201556% built
15 February 201550% built
18 December 201441% built
12 July 201432% built
21 January 201425% built
3 September 201325% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.