The One Hotel construction progress

The register lists The One Hotel in Business Bay as complete, with a registered completion date of May 2020. Its last site inspection on record was in October 2020. The developer is T F G Real Estate.

100%

Built, at the site inspection of 11 October 2020

Construction complete

Registered completion date
May 2020
Construction started
December 2016
First registered
March 2017
Developer
T F G Real Estate
Community
Business Bay
Units
504
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ذا وان هوتيل
Project number
1864
Site inspections
11

Schedule

The register lists The One Hotel as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 October 2020

100%+4.9 pts

  • The One Hotel construction site, inspection photo 1, 11 October 2020
  • The One Hotel construction site, inspection photo 2, 11 October 2020
  • The One Hotel construction site, inspection photo 3, 11 October 2020
  • The One Hotel construction site, inspection photo 4, 11 October 2020

20 April 2020

95%+5.0 pts

  • The One Hotel construction site, inspection photo 1, 20 April 2020
  • The One Hotel construction site, inspection photo 2, 20 April 2020
  • The One Hotel construction site, inspection photo 3, 20 April 2020
  • The One Hotel construction site, inspection photo 4, 20 April 2020

17 December 2019

90%+13 pts

  • The One Hotel construction site, inspection photo 1, 17 December 2019
  • The One Hotel construction site, inspection photo 2, 17 December 2019
  • The One Hotel construction site, inspection photo 3, 17 December 2019
  • The One Hotel construction site, inspection photo 4, 17 December 2019

4 September 2019

77%+17 pts

  • The One Hotel construction site, inspection photo 1, 4 September 2019
  • The One Hotel construction site, inspection photo 2, 4 September 2019
  • The One Hotel construction site, inspection photo 3, 4 September 2019
  • The One Hotel construction site, inspection photo 4, 4 September 2019

19 May 2019

60%+17 pts

  • The One Hotel construction site, inspection photo 1, 19 May 2019
  • The One Hotel construction site, inspection photo 2, 19 May 2019
  • The One Hotel construction site, inspection photo 3, 19 May 2019
  • The One Hotel construction site, inspection photo 4, 19 May 2019

17 January 2019

43%+12 pts

  • The One Hotel construction site, inspection photo 1, 17 January 2019
  • The One Hotel construction site, inspection photo 2, 17 January 2019
  • The One Hotel construction site, inspection photo 3, 17 January 2019
  • The One Hotel construction site, inspection photo 4, 17 January 2019

4 October 2018

32%+12 pts

  • The One Hotel construction site, inspection photo 1, 4 October 2018
  • The One Hotel construction site, inspection photo 2, 4 October 2018
  • The One Hotel construction site, inspection photo 3, 4 October 2018
  • The One Hotel construction site, inspection photo 4, 4 October 2018

19 June 2018

20%+4.4 pts

  • The One Hotel construction site, inspection photo 1, 19 June 2018
  • The One Hotel construction site, inspection photo 2, 19 June 2018
  • The One Hotel construction site, inspection photo 3, 19 June 2018
  • The One Hotel construction site, inspection photo 4, 19 June 2018

17 April 2018

16%+8.1 pts

  • The One Hotel construction site, inspection photo 1, 17 April 2018
  • The One Hotel construction site, inspection photo 2, 17 April 2018
  • The One Hotel construction site, inspection photo 3, 17 April 2018
  • The One Hotel construction site, inspection photo 4, 17 April 2018

11 January 2018

7.6%+2.5 pts

  • The One Hotel construction site, inspection photo 1, 11 January 2018
  • The One Hotel construction site, inspection photo 2, 11 January 2018
  • The One Hotel construction site, inspection photo 3, 11 January 2018
  • The One Hotel construction site, inspection photo 4, 11 January 2018

All 110 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in The One Hotel?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The One Hotel handover date?
Construction of The One Hotel is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The One Hotel?
The One Hotel was 100% built at the site inspection on 11 October 2020. The site has been inspected 11 times since September 2017. The Land Department took 110 site photos at its inspections.
Is The One Hotel delayed?
The register lists construction as complete.
Who is building The One Hotel?
The registered developer is T F G Real Estate.
Which bank holds the escrow account for The One Hotel?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.