The One Hotel construction photos

110 photos from 11 site inspections, newest first. The percentage is how much of The One Hotel was built on the day of each visit.

11 October 2020100% built

20 April 202095% built

17 December 201990% built

4 September 201977% built

19 May 201960% built

17 January 201943% built

4 October 201832% built

19 June 201820% built

17 April 201816% built

11 January 20187.6% built

28 September 20175.1% built

Back to The One Hotel construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.