The Exchange construction progress

The register lists The Exchange in Business Bay as complete, with a registered completion date of October 2015. Its last site inspection on record was in April 2015. The developer is Tanmiyat Global Real Estate Development.

100%

Built, at the site inspection of 2 April 2015

Construction complete

Registered completion date
October 2015
Construction started
September 2007
First registered
November 2008
Developer
Tanmiyat Global Real Estate Development
Community
Business Bay
Units
188
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
اكستشانج
Project number
490
Site inspections
8

Schedule

The register lists The Exchange as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2008201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 April 2015

87%+12 pts

  • The Exchange construction site, inspection photo 1, 2 April 2015
  • The Exchange construction site, inspection photo 2, 2 April 2015
  • The Exchange construction site, inspection photo 3, 2 April 2015
  • The Exchange construction site, inspection photo 4, 2 April 2015

27 November 2014

75%+15 pts

  • The Exchange construction site, inspection photo 1, 27 November 2014
  • The Exchange construction site, inspection photo 2, 27 November 2014
  • The Exchange construction site, inspection photo 3, 27 November 2014
  • The Exchange construction site, inspection photo 4, 27 November 2014

9 August 2014

61%+6.9 pts

  • The Exchange construction site, inspection photo 1, 9 August 2014
  • The Exchange construction site, inspection photo 2, 9 August 2014
  • The Exchange construction site, inspection photo 3, 9 August 2014
  • The Exchange construction site, inspection photo 4, 9 August 2014

22 May 2014

54%+11 pts

  • The Exchange construction site, inspection photo 1, 22 May 2014
  • The Exchange construction site, inspection photo 2, 22 May 2014
  • The Exchange construction site, inspection photo 3, 22 May 2014
  • The Exchange construction site, inspection photo 4, 22 May 2014

31 October 2013

43%+3.2 pts

  • The Exchange construction site, inspection photo 1, 31 October 2013
  • The Exchange construction site, inspection photo 2, 31 October 2013
  • The Exchange construction site, inspection photo 3, 31 October 2013
  • The Exchange construction site, inspection photo 4, 31 October 2013

21 May 2013

40%+8.0 pts

  • The Exchange construction site, inspection photo 1, 21 May 2013
  • The Exchange construction site, inspection photo 2, 21 May 2013
  • The Exchange construction site, inspection photo 3, 21 May 2013
  • The Exchange construction site, inspection photo 4, 21 May 2013

25 November 2012

32%+4.0 pts

  • The Exchange construction site, inspection photo 1, 25 November 2012
  • The Exchange construction site, inspection photo 2, 25 November 2012
  • The Exchange construction site, inspection photo 3, 25 November 2012
  • The Exchange construction site, inspection photo 4, 25 November 2012

26 August 2012

28%

  • The Exchange construction site, inspection photo 1, 26 August 2012
  • The Exchange construction site, inspection photo 2, 26 August 2012
  • The Exchange construction site, inspection photo 3, 26 August 2012
  • The Exchange construction site, inspection photo 4, 26 August 2012

All 65 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Tanmiyat Global Real Estate Development has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Exchange?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Exchange handover date?
Construction of The Exchange is recorded as complete, with a registered completion date of October 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Exchange?
The Exchange was 100% built at the site inspection on 2 April 2015. The site has been inspected 8 times since August 2012. The Land Department took 65 site photos at its inspections.
Is The Exchange delayed?
The register lists construction as complete.
Who is building The Exchange?
The registered developer is Tanmiyat Global Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Exchange?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.