Living Legends Phase 7 construction progress

Living Legends Phase 7 in Living Legends is 92% built at the Land Department inspection of January 2022. Developer Tanmiyat Global Real Estate Development. Completion registered for September 2021.

92%

Built, at the Land Department site inspection of 27 January 2022

60 months past its registered completion date

Completion date (Land Department)
September 2021
Finish at recent pace
March 2052
Construction started
June 2011
Registered with the Land Department
June 2012
Developer
Tanmiyat Global Real Estate Development
Units
343
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
الأساطير الحية المرحلة 7
Land Department project number
1326
Land Department site inspections
19

Schedule

Living Legends Phase 7 was registered to complete in September 2021, 60 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around March 2052.

0%25%50%75%100%201220142016201820202022
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 January 2022

92%

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 27 January 2022
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 27 January 2022
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 27 January 2022
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 27 January 2022

2 August 2021

92%+0.3 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 2 August 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 2 August 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 2 August 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 2 August 2021

9 February 2021

92%+0.8 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 9 February 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 9 February 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 9 February 2021
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 9 February 2021

15 October 2020

91%+3.2 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 15 October 2020
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 15 October 2020
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 15 October 2020
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 15 October 2020

8 May 2019

88%+5.3 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 8 May 2019
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 8 May 2019
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 8 May 2019
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 8 May 2019

11 December 2018

82%+1.9 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 11 December 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 11 December 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 11 December 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 11 December 2018

29 July 2018

80%+9.6 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 29 July 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 29 July 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 29 July 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 29 July 2018

18 February 2018

71%+2.6 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 18 February 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 18 February 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 18 February 2018
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 18 February 2018

12 September 2017

68%+0.9 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 12 September 2017
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 12 September 2017
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 12 September 2017
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 12 September 2017

21 November 2016

67%+3.7 pts

  • Living Legends Phase 7 construction site, Land Department inspection photo 1, 21 November 2016
  • Living Legends Phase 7 construction site, Land Department inspection photo 2, 21 November 2016
  • Living Legends Phase 7 construction site, Land Department inspection photo 3, 21 November 2016
  • Living Legends Phase 7 construction site, Land Department inspection photo 4, 21 November 2016

All 188 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average. Living Legends Phase 7 is ahead of that average.

Own a unit in Living Legends Phase 7?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Living Legends Phase 7 be completed?
The completion date registered with the Dubai Land Department is September 2021. At the pace of its recent inspections the site would reach 100% around March 2052. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Living Legends Phase 7 is built?
92%, measured at the Land Department site inspection on 27 January 2022. The Land Department engineers have inspected the site 19 times since November 2012.
Is Living Legends Phase 7 delayed?
Yes. Its registered completion date of September 2021 has passed and the Land Department still lists it as under construction.
Who is building Living Legends Phase 7?
The registered developer is Tanmiyat Global Real Estate Development.
Which bank holds the escrow account for Living Legends Phase 7?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.