Living Legends Phase 7 construction progress
Living Legends Phase 7 in Living Legends is 92% built at the Land Department inspection of January 2022. Developer Tanmiyat Global Real Estate Development. Completion registered for September 2021.
92%
Built, at the Land Department site inspection of 27 January 2022
60 months past its registered completion date
- Completion date (Land Department)
- September 2021
- Finish at recent pace
- March 2052
- Construction started
- June 2011
- Registered with the Land Department
- June 2012
- Developer
- Tanmiyat Global Real Estate Development
- Community
- Living Legends
- Units
- 343
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- الأساطير الحية المرحلة 7
- Land Department project number
- 1326
- Land Department site inspections
- 19
Schedule
Living Legends Phase 7 was registered to complete in September 2021, 60 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around March 2052.
Site inspections
27 January 2022
92%
2 August 2021
92%+0.3 pts
9 February 2021
92%+0.8 pts
15 October 2020
91%+3.2 pts
8 May 2019
88%+5.3 pts
11 December 2018
82%+1.9 pts
29 July 2018
80%+9.6 pts
18 February 2018
71%+2.6 pts
12 September 2017
68%+0.9 pts
21 November 2016
67%+3.7 pts
Context
Living Legends has 6 projects under construction, 49% built on average. Living Legends Phase 7 is ahead of that average.
Own a unit in Living Legends Phase 7?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Living Legends Phase 7 be completed?
- The completion date registered with the Dubai Land Department is September 2021. At the pace of its recent inspections the site would reach 100% around March 2052. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Living Legends Phase 7 is built?
- 92%, measured at the Land Department site inspection on 27 January 2022. The Land Department engineers have inspected the site 19 times since November 2012.
- Is Living Legends Phase 7 delayed?
- Yes. Its registered completion date of September 2021 has passed and the Land Department still lists it as under construction.
- Who is building Living Legends Phase 7?
- The registered developer is Tanmiyat Global Real Estate Development.
- Which bank holds the escrow account for Living Legends Phase 7?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Living Legends Phase 4Nearby in Living Legends. 62%, Due March 2027.
- Living Legends Phase 5Nearby in Living Legends. 49%, Due March 2025, passed.
- Living Legends Phase 6Nearby in Living Legends. 77%, Due July 2026, passed.
- The Wilds 1Nearby in Living Legends. 7.5%, Due January 2029.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)