The Court construction progress
The register lists The Court in Business Bay as complete, with a registered completion date of March 2021. Its last site inspection on record was in February 2021. The developer is Tanmiyat Global Real Estate Development.
100%
Built, at the site inspection of 4 February 2021
Construction complete
- Registered completion date
- March 2021
- Construction started
- July 2008
- First registered
- November 2008
- Developer
- Tanmiyat Global Real Estate Development
- Community
- Business Bay
- Units
- 271
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- المحكمة
- Project number
- 488
- Site inspections
- 17
Schedule
The register lists The Court as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
4 February 2021
99%+5.0 pts
25 February 2019
94%+2.7 pts
19 December 2018
91%+3.6 pts
29 July 2018
87%+4.3 pts
22 February 2018
83%+2.0 pts
5 September 2017
81%+2.7 pts
27 December 2016
78%+7.4 pts
9 August 2016
71%+5.8 pts
13 April 2016
65%+11 pts
25 January 2016
54%+8.5 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Tanmiyat Global Real Estate Development has 1 project under construction in Dubai; 1 has passed its registered completion date.
Own a unit in The Court?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the The Court handover date?
- Construction of The Court is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on The Court?
- The Court was 100% built at the site inspection on 4 February 2021. The site has been inspected 17 times since May 2012. The Land Department took 141 site photos at its inspections.
- Is The Court delayed?
- The register lists construction as complete.
- Who is building The Court?
- The registered developer is Tanmiyat Global Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Court?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Living Legends Phase 7Also by Tanmiyat Global Real Estate Development. 92%, Due September 2021, passed.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)