Terraces Marasi Drive construction progress

The register lists Terraces Marasi Drive in Business Bay as complete, with a registered completion date of June 2024. Its last site inspection on record was in October 2024. The developer is Key Mavens For Real Estate Development.

100%

Built, at the site inspection of 1 October 2024

Construction complete

Registered completion date
June 2024
Construction started
March 2022
First registered
March 2023
Developer
Key Mavens For Real Estate Development
Community
Business Bay
Units
125
Escrow bank
Al Masraf
Name in Arabic
تيراسيس مراسي درايف
Project number
2568
Site inspections
5

Schedule

The register lists Terraces Marasi Drive as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2024

100%+10.0 pts

  • Terraces Marasi Drive construction site, inspection photo 1, 1 October 2024
  • Terraces Marasi Drive construction site, inspection photo 2, 1 October 2024
  • Terraces Marasi Drive construction site, inspection photo 3, 1 October 2024
  • Terraces Marasi Drive construction site, inspection photo 4, 1 October 2024

29 April 2024

90%+26 pts

  • Terraces Marasi Drive construction site, inspection photo 1, 29 April 2024
  • Terraces Marasi Drive construction site, inspection photo 2, 29 April 2024
  • Terraces Marasi Drive construction site, inspection photo 3, 29 April 2024
  • Terraces Marasi Drive construction site, inspection photo 4, 29 April 2024

19 October 2023

64%+17 pts

  • Terraces Marasi Drive construction site, inspection photo 1, 19 October 2023
  • Terraces Marasi Drive construction site, inspection photo 2, 19 October 2023
  • Terraces Marasi Drive construction site, inspection photo 3, 19 October 2023
  • Terraces Marasi Drive construction site, inspection photo 4, 19 October 2023

8 August 2023

46%+16 pts

  • Terraces Marasi Drive construction site, inspection photo 1, 8 August 2023
  • Terraces Marasi Drive construction site, inspection photo 2, 8 August 2023
  • Terraces Marasi Drive construction site, inspection photo 3, 8 August 2023
  • Terraces Marasi Drive construction site, inspection photo 4, 8 August 2023

6 February 2023

30%

  • Terraces Marasi Drive construction site, inspection photo 1, 6 February 2023
  • Terraces Marasi Drive construction site, inspection photo 2, 6 February 2023
  • Terraces Marasi Drive construction site, inspection photo 3, 6 February 2023
  • Terraces Marasi Drive construction site, inspection photo 4, 6 February 2023

All 51 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Terraces Marasi Drive?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Terraces Marasi Drive handover date?
Construction of Terraces Marasi Drive is recorded as complete, with a registered completion date of June 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Terraces Marasi Drive?
Terraces Marasi Drive was 100% built at the site inspection on 1 October 2024. The site has been inspected 5 times since February 2023. The Land Department took 51 site photos at its inspections.
Is Terraces Marasi Drive delayed?
The register lists construction as complete.
Who is building Terraces Marasi Drive?
The registered developer is Key Mavens For Real Estate Development.
Which bank holds the escrow account for Terraces Marasi Drive?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.