Mag 318 construction progress

The register lists Mag 318 in Business Bay as complete, with a registered completion date of December 2020. Its last site inspection on record was in December 2020. The developer is Mag Property Development.

100%

Built, at the site inspection of 6 December 2020

Construction complete

Registered completion date
December 2020
Construction started
October 2017
First registered
May 2017
Developer
Mag Property Development
Community
Business Bay
Units
451
Escrow bank
Emirates NBD
Name in Arabic
ماج 318
Project number
1891
Site inspections
8

Schedule

The register lists Mag 318 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 December 2020

100%+9.9 pts

  • Mag 318 construction site, inspection photo 1, 6 December 2020
  • Mag 318 construction site, inspection photo 2, 6 December 2020
  • Mag 318 construction site, inspection photo 3, 6 December 2020
  • Mag 318 construction site, inspection photo 4, 6 December 2020

24 August 2020

90%+8.0 pts

  • Mag 318 construction site, inspection photo 1, 24 August 2020
  • Mag 318 construction site, inspection photo 2, 24 August 2020
  • Mag 318 construction site, inspection photo 3, 24 August 2020
  • Mag 318 construction site, inspection photo 4, 24 August 2020

3 June 2020

82%+32 pts

  • Mag 318 construction site, inspection photo 1, 3 June 2020
  • Mag 318 construction site, inspection photo 2, 3 June 2020
  • Mag 318 construction site, inspection photo 3, 3 June 2020
  • Mag 318 construction site, inspection photo 4, 3 June 2020

31 October 2019

50%+20 pts

  • Mag 318 construction site, inspection photo 1, 31 October 2019
  • Mag 318 construction site, inspection photo 2, 31 October 2019
  • Mag 318 construction site, inspection photo 3, 31 October 2019
  • Mag 318 construction site, inspection photo 4, 31 October 2019

27 June 2019

30%+13 pts

  • Mag 318 construction site, inspection photo 1, 27 June 2019
  • Mag 318 construction site, inspection photo 2, 27 June 2019
  • Mag 318 construction site, inspection photo 3, 27 June 2019
  • Mag 318 construction site, inspection photo 4, 27 June 2019

18 February 2019

17%+13 pts

  • Mag 318 construction site, inspection photo 1, 18 February 2019
  • Mag 318 construction site, inspection photo 2, 18 February 2019
  • Mag 318 construction site, inspection photo 3, 18 February 2019
  • Mag 318 construction site, inspection photo 4, 18 February 2019

16 September 2018

3.6%+2.8 pts

  • Mag 318 construction site, inspection photo 1, 16 September 2018
  • Mag 318 construction site, inspection photo 2, 16 September 2018
  • Mag 318 construction site, inspection photo 3, 16 September 2018
  • Mag 318 construction site, inspection photo 4, 16 September 2018

2 April 2018

0.8%

  • Mag 318 construction site, inspection photo 1, 2 April 2018
  • Mag 318 construction site, inspection photo 2, 2 April 2018
  • Mag 318 construction site, inspection photo 3, 2 April 2018
  • Mag 318 construction site, inspection photo 4, 2 April 2018

All 89 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Mag 318?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mag 318 handover date?
Construction of Mag 318 is recorded as complete, with a registered completion date of December 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mag 318?
Mag 318 was 100% built at the site inspection on 6 December 2020. The site has been inspected 8 times since April 2018. The Land Department took 89 site photos at its inspections.
Is Mag 318 delayed?
The register lists construction as complete.
Who is building Mag 318?
The registered developer is Mag Property Development.
Which bank holds the escrow account for Mag 318?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.