Mag 318 construction photos

89 photos from 8 site inspections, newest first. The percentage is how much of Mag 318 was built on the day of each visit.

6 December 2020100% built

24 August 202090% built

3 June 202082% built

31 October 201950% built

27 June 201930% built

18 February 201917% built

16 September 20183.6% built

2 April 20180.8% built

Back to Mag 318 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.