J One construction progress

The register lists J One in Business Bay as complete, with a registered completion date of December 2021. Its last site inspection on record was in December 2021. The developer is Rkm Durar Properties.

100%

Built, at the site inspection of 28 December 2021

Construction complete

Registered completion date
December 2021
Construction started
June 2016
First registered
August 2017
Developer
Rkm Durar Properties
Community
Business Bay
Units
353
Escrow bank
Commercial Bank of Dubai
Name in Arabic
جي ون
Project number
1913
Site inspections
11

Schedule

The register lists J One as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 December 2021

100%+4.5 pts

  • J One construction site, inspection photo 1, 28 December 2021
  • J One construction site, inspection photo 2, 28 December 2021
  • J One construction site, inspection photo 3, 28 December 2021
  • J One construction site, inspection photo 4, 28 December 2021

2 September 2021

96%+2.4 pts

  • J One construction site, inspection photo 1, 2 September 2021
  • J One construction site, inspection photo 2, 2 September 2021
  • J One construction site, inspection photo 3, 2 September 2021
  • J One construction site, inspection photo 4, 2 September 2021

18 February 2021

93%+3.1 pts

  • J One construction site, inspection photo 1, 18 February 2021
  • J One construction site, inspection photo 2, 18 February 2021
  • J One construction site, inspection photo 3, 18 February 2021
  • J One construction site, inspection photo 4, 18 February 2021

28 July 2020

90%+6.3 pts

  • J One construction site, inspection photo 1, 28 July 2020
  • J One construction site, inspection photo 2, 28 July 2020
  • J One construction site, inspection photo 3, 28 July 2020
  • J One construction site, inspection photo 4, 28 July 2020

10 March 2020

84%+13 pts

  • J One construction site, inspection photo 1, 10 March 2020
  • J One construction site, inspection photo 2, 10 March 2020
  • J One construction site, inspection photo 3, 10 March 2020
  • J One construction site, inspection photo 4, 10 March 2020

21 October 2019

71%+10 pts

  • J One construction site, inspection photo 1, 21 October 2019
  • J One construction site, inspection photo 2, 21 October 2019
  • J One construction site, inspection photo 3, 21 October 2019
  • J One construction site, inspection photo 4, 21 October 2019

12 June 2019

60%+13 pts

  • J One construction site, inspection photo 1, 12 June 2019
  • J One construction site, inspection photo 2, 12 June 2019
  • J One construction site, inspection photo 3, 12 June 2019
  • J One construction site, inspection photo 4, 12 June 2019

23 January 2019

47%+17 pts

  • J One construction site, inspection photo 1, 23 January 2019
  • J One construction site, inspection photo 2, 23 January 2019
  • J One construction site, inspection photo 3, 23 January 2019
  • J One construction site, inspection photo 4, 23 January 2019

17 September 2018

30%+6.8 pts

  • J One construction site, inspection photo 1, 17 September 2018
  • J One construction site, inspection photo 2, 17 September 2018
  • J One construction site, inspection photo 3, 17 September 2018
  • J One construction site, inspection photo 4, 17 September 2018

3 May 2018

24%+3.5 pts

  • J One construction site, inspection photo 1, 3 May 2018
  • J One construction site, inspection photo 2, 3 May 2018
  • J One construction site, inspection photo 3, 3 May 2018

All 110 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in J One?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the J One handover date?
Construction of J One is recorded as complete, with a registered completion date of December 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on J One?
J One was 100% built at the site inspection on 28 December 2021. The site has been inspected 11 times since January 2018. The Land Department took 110 site photos at its inspections.
Is J One delayed?
The register lists construction as complete.
Who is building J One?
The registered developer is Rkm Durar Properties.
Which bank holds the escrow account for J One?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.