J One construction photos

110 photos from 11 site inspections, newest first. The percentage is how much of J One was built on the day of each visit.

28 December 2021100% built

2 September 202196% built

18 February 202193% built

28 July 202090% built

10 March 202084% built

21 October 201971% built

12 June 201960% built

23 January 201947% built

17 September 201830% built

3 May 201824% built

8 January 201820% built

Back to J One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.