Eywa Dubai construction photos

109 photos taken by Dubai Land Department engineers at 14 site inspections, newest first. The percentage is how much of Eywa Dubai was built on the day of each visit.

21 September 202664% built

31 August 202662% built

6 July 202660% built

11 June 202657% built

19 May 202656% built

29 April 202652% built

25 March 202648% built

26 January 202640% built

28 October 202534% built

25 July 202527% built

7 April 202520% built

29 January 202515% built

6 September 20248.0% built

22 March 20230% built

Back to Eywa Dubai construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.