62 photos from 11 site inspections, newest first. The percentage is how much of Chic Tower was built on the day of each visit.

17 August 202684% built

8 April 202674% built

11 December 202559% built

4 August 202548% built

10 April 202530% built

21 January 202519% built

5 July 202415% built

14 March 20247.3% built

9 August 20234.0% built

11 April 20230.1% built

15 September 20220% built

Back to Chic Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.