Canal Crown construction photos

47 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Canal Crown was built on the day of each visit.

15 July 202642% built

12 March 202633% built

7 October 202523% built

30 May 202518% built

22 January 202512% built

5 July 20248.5% built

1 November 20230.2% built

13 April 20230% built

Back to Canal Crown construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.