Wynwood Horizon By Imtiaz construction progress
The registered completion date for Wynwood Horizon By Imtiaz in Bukadra is October 2028. At the last site inspection, in September 2026, it was 9.6% built. The developer is Imtiaz Gi Real Estate Development.
9.6%
Built, at the site inspection of 16 September 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- October 2035
- Construction started
- November 2025
- First registered
- October 2025
- Developer
- Imtiaz Gi Real Estate Development
- Community
- Bukadra
- Units
- 165
- Escrow bank
- Ajman Bank
- Name in Arabic
- وينوود هورايزون من امتياز
- Project number
- 4133
- Site inspections
- 4
Schedule
Between September 2025 and September 2026 the site added about 0.8 points a month. At that rate it would finish around October 2035, more than three months after its registered date of October 2028.
Site inspections
16 September 2026
9.6%+2.9 pts
16 June 2026
6.7%+6.0 pts
17 March 2026
0.6%+0.6 pts
30 September 2025
0%
Context
Bukadra has 21 projects under construction, 27% built on average.
Imtiaz Gi Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Wynwood Horizon By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Wynwood Horizon By Imtiaz handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Wynwood Horizon By Imtiaz?
- Wynwood Horizon By Imtiaz was 9.6% built at the site inspection on 16 September 2026. The site has been inspected 4 times since September 2025. The Land Department took 13 site photos at its inspections.
- Is Wynwood Horizon By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Wynwood Horizon By Imtiaz?
- The registered developer is Imtiaz Gi Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Wynwood Horizon By Imtiaz?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Wynwood Residences By ImtiazAlso by Imtiaz Gi Real Estate Development. 26%, Due September 2027.
- 330 Riverside CrescentNearby in Bukadra. 68%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)