Wynwood Residences By Imtiaz construction progress

The registered completion date for Wynwood Residences By Imtiaz in Palm Deira is September 2027. At the last site inspection, in October 2026, it was 26% built. The developer is Imtiaz Gi Real Estate Development.

26%

Built, at the site inspection of 6 October 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
July 2029
Construction started
June 2025
First registered
July 2025
Developer
Imtiaz Gi Real Estate Development
Community
Palm Deira
Units
146
Escrow bank
Ajman Bank
Name in Arabic
وينوود ريزيدنسز من امتياز
Project number
3784
Site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 2.2 points a month. At that rate it would finish around July 2029, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 October 2026

26%+10 pts

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 6 October 2026

9 July 2026

16%+7.6 pts

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 9 July 2026

3 April 2026

8.4%+3.1 pts

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 3 April 2026

24 December 2025

5.4%+4.6 pts

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 24 December 2025

9 September 2025

0.7%+0.7 pts

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 9 September 2025

20 May 2025

0%

  • Wynwood Residences By Imtiaz construction site, inspection photo 1, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 2, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 3, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, inspection photo 4, 20 May 2025

All 31 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Gi Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Wynwood Residences By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Wynwood Residences By Imtiaz handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Wynwood Residences By Imtiaz?
Wynwood Residences By Imtiaz was 26% built at the site inspection on 6 October 2026. The site has been inspected 6 times since May 2025. The Land Department took 31 site photos at its inspections.
Is Wynwood Residences By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Wynwood Residences By Imtiaz?
The registered developer is Imtiaz Gi Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Wynwood Residences By Imtiaz?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.