Wynwood Residences By Imtiaz construction progress

Wynwood Residences By Imtiaz in Palm Deira is 26% built at the Land Department inspection of October 2026. Developer Imtiaz Gi Real Estate Development. Completion registered for September 2027.

26%

Built, at the Land Department site inspection of 6 October 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
July 2029
Construction started
June 2025
Registered with the Land Department
July 2025
Developer
Imtiaz Gi Real Estate Development
Community
Palm Deira
Units
146
Escrow bank
Ajman Bank
Name in Arabic
وينوود ريزيدنسز من امتياز
Land Department project number
3784
Land Department site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 2.2 points a month. At that rate it would finish around July 2029, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 October 2026

26%+10 pts

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 6 October 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 6 October 2026

9 July 2026

16%+7.6 pts

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 9 July 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 9 July 2026

3 April 2026

8.4%+3.1 pts

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 3 April 2026
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 3 April 2026

24 December 2025

5.4%+4.6 pts

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 24 December 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 24 December 2025

9 September 2025

0.7%+0.7 pts

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 9 September 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 9 September 2025

20 May 2025

0%

  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 1, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 2, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 3, 20 May 2025
  • Wynwood Residences By Imtiaz construction site, Land Department inspection photo 4, 20 May 2025

All 31 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Imtiaz Gi Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Wynwood Residences By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Wynwood Residences By Imtiaz be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around July 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Wynwood Residences By Imtiaz is built?
26%, measured at the Land Department site inspection on 6 October 2026. The Land Department engineers have inspected the site 6 times since May 2025.
Is Wynwood Residences By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Wynwood Residences By Imtiaz?
The registered developer is Imtiaz Gi Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Wynwood Residences By Imtiaz?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.