Trinity By Karma construction photos
44 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Trinity By Karma was built on the day of each visit.
30 September 202631% built
6 May 202622% built
6 January 202618% built
2 September 202514% built
13 March 20251.6% built
12 November 20240% built
22 January 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.