99 Park Place construction progress

99 Park Place in Jumeirah Village Circle was registered to complete in December 2025 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is Tabeer Real Estate Development.

90%

Built, at the site inspection of 12 October 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
December 2026
Construction started
February 2024
First registered
May 2024
Units
102
Escrow bank
Emirates Islamic Bank
Name in Arabic
99 Park Place
Project number
2968
Site inspections
8

Schedule

99 Park Place was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

90%+9.4 pts

  • 99 Park Place construction site, inspection photo 1, 12 October 2026
  • 99 Park Place construction site, inspection photo 2, 12 October 2026
  • 99 Park Place construction site, inspection photo 3, 12 October 2026
  • 99 Park Place construction site, inspection photo 4, 12 October 2026

8 June 2026

81%+21 pts

  • 99 Park Place construction site, inspection photo 1, 8 June 2026
  • 99 Park Place construction site, inspection photo 2, 8 June 2026
  • 99 Park Place construction site, inspection photo 3, 8 June 2026
  • 99 Park Place construction site, inspection photo 4, 8 June 2026

21 January 2026

60%+21 pts

  • 99 Park Place construction site, inspection photo 1, 21 January 2026
  • 99 Park Place construction site, inspection photo 2, 21 January 2026
  • 99 Park Place construction site, inspection photo 3, 21 January 2026
  • 99 Park Place construction site, inspection photo 4, 21 January 2026

20 October 2025

39%+16 pts

  • 99 Park Place construction site, inspection photo 1, 20 October 2025
  • 99 Park Place construction site, inspection photo 2, 20 October 2025
  • 99 Park Place construction site, inspection photo 3, 20 October 2025
  • 99 Park Place construction site, inspection photo 4, 20 October 2025

21 May 2025

23%+11 pts

  • 99 Park Place construction site, inspection photo 1, 21 May 2025
  • 99 Park Place construction site, inspection photo 2, 21 May 2025
  • 99 Park Place construction site, inspection photo 3, 21 May 2025
  • 99 Park Place construction site, inspection photo 4, 21 May 2025

25 February 2025

12%+4.1 pts

  • 99 Park Place construction site, inspection photo 1, 25 February 2025
  • 99 Park Place construction site, inspection photo 2, 25 February 2025
  • 99 Park Place construction site, inspection photo 3, 25 February 2025
  • 99 Park Place construction site, inspection photo 4, 25 February 2025

18 December 2024

7.9%+7.9 pts

  • 99 Park Place construction site, inspection photo 1, 18 December 2024
  • 99 Park Place construction site, inspection photo 2, 18 December 2024
  • 99 Park Place construction site, inspection photo 3, 18 December 2024

12 March 2024

0%

  • 99 Park Place construction site, inspection photo 1, 12 March 2024
  • 99 Park Place construction site, inspection photo 2, 12 March 2024
  • 99 Park Place construction site, inspection photo 3, 12 March 2024

All 60 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Tabeer Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in 99 Park Place?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 99 Park Place handover date?
The registered completion date was December 2025, and the register still lists 99 Park Place as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on 99 Park Place?
99 Park Place was 90% built at the site inspection on 12 October 2026. The site has been inspected 8 times since March 2024. The Land Department took 60 site photos at its inspections.
Is 99 Park Place delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building 99 Park Place?
The registered developer is Tabeer Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for 99 Park Place?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.