99 Park Place construction progress
99 Park Place in Jumeirah Village Circle was registered to complete in December 2025 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is Tabeer Real Estate Development.
90%
Built, at the site inspection of 12 October 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- December 2026
- Construction started
- February 2024
- First registered
- May 2024
- Developer
- Tabeer Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 102
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- 99 Park Place
- Project number
- 2968
- Site inspections
- 8
Schedule
99 Park Place was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
12 October 2026
90%+9.4 pts
8 June 2026
81%+21 pts
21 January 2026
60%+21 pts
20 October 2025
39%+16 pts
21 May 2025
23%+11 pts
25 February 2025
12%+4.1 pts
18 December 2024
7.9%+7.9 pts
12 March 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Tabeer Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in 99 Park Place?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 99 Park Place handover date?
- The registered completion date was December 2025, and the register still lists 99 Park Place as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 99 Park Place?
- 99 Park Place was 90% built at the site inspection on 12 October 2026. The site has been inspected 8 times since March 2024. The Land Department took 60 site photos at its inspections.
- Is 99 Park Place delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building 99 Park Place?
- The registered developer is Tabeer Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for 99 Park Place?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Parkside BoulevardAlso by Tabeer Real Estate Development. 60%, Due December 2027.
- 368 Park LnAlso by Tabeer Real Estate Development. 1.7%, Due August 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)











.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)