Legacy By Sunrise construction progress

The register lists Legacy By Sunrise in Arjan as complete, with a registered completion date of May 2024. Its last site inspection on record was in July 2024. The developer is Sunrise Capital Real Estate Development.

100%

Built, at the site inspection of 9 July 2024

Construction complete

Registered completion date
May 2024
Construction started
October 2022
First registered
September 2023
Developer
Sunrise Capital Real Estate Development
Community
Arjan
Units
132
Escrow bank
Mashreq Bank
Name in Arabic
ليغاسي باي سنرايس
Project number
2632
Site inspections
3

Schedule

The register lists Legacy By Sunrise as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 July 2024

100%+35 pts

  • Legacy By Sunrise construction site, inspection photo 1, 9 July 2024
  • Legacy By Sunrise construction site, inspection photo 2, 9 July 2024
  • Legacy By Sunrise construction site, inspection photo 3, 9 July 2024
  • Legacy By Sunrise construction site, inspection photo 4, 9 July 2024

30 November 2023

65%+29 pts

  • Legacy By Sunrise construction site, inspection photo 1, 30 November 2023
  • Legacy By Sunrise construction site, inspection photo 2, 30 November 2023
  • Legacy By Sunrise construction site, inspection photo 3, 30 November 2023
  • Legacy By Sunrise construction site, inspection photo 4, 30 November 2023

4 July 2023

36%

  • Legacy By Sunrise construction site, inspection photo 1, 4 July 2023
  • Legacy By Sunrise construction site, inspection photo 2, 4 July 2023
  • Legacy By Sunrise construction site, inspection photo 3, 4 July 2023
  • Legacy By Sunrise construction site, inspection photo 4, 4 July 2023

All 32 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Sunrise Capital Real Estate Development has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Legacy By Sunrise?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Legacy By Sunrise handover date?
Construction of Legacy By Sunrise is recorded as complete, with a registered completion date of May 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Legacy By Sunrise?
Legacy By Sunrise was 100% built at the site inspection on 9 July 2024. The site has been inspected 3 times since July 2023. The Land Department took 32 site photos at its inspections.
Is Legacy By Sunrise delayed?
The register lists construction as complete.
Who is building Legacy By Sunrise?
The registered developer is Sunrise Capital Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Legacy By Sunrise?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.