Bellavion By Sunrise construction progress
The registered completion date for Bellavion By Sunrise in Wasl Gate is December 2027. At the last site inspection, in November 2026, it was 19% built. The developer is Sunrise Capital Real Estate Development.
19%
Built, at the site inspection of 12 November 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- August 2030
- Construction started
- May 2025
- First registered
- March 2025
- Developer
- Sunrise Capital Real Estate Development
- Community
- Wasl Gate
- Units
- 275
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بيلافيون باي صانرايز
- Project number
- 3472
- Site inspections
- 4
Schedule
Between February 2026 and November 2026 the site added about 1.8 points a month. At that rate it would finish around August 2030, more than three months after its registered date of December 2027.
Site inspections
12 November 2026
19%+8.3 pts
8 June 2026
10%+7.5 pts
17 February 2026
2.8%+2.8 pts
6 January 2025
0%
Context
Wasl Gate has 13 projects under construction, 21% built on average.
Own a unit in Bellavion By Sunrise?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bellavion By Sunrise handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bellavion By Sunrise?
- Bellavion By Sunrise was 19% built at the site inspection on 12 November 2026. The site has been inspected 4 times since January 2025. The Land Department took 19 site photos at its inspections.
- Is Bellavion By Sunrise delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Bellavion By Sunrise?
- The registered developer is Sunrise Capital Real Estate Development.
- Which bank holds the escrow account for Bellavion By Sunrise?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Hillside Residences 1Nearby in Wasl Gate. 26%.
- Hillside Residences 2Nearby in Wasl Gate. 18%.
- Hillside Residences 3Nearby in Wasl Gate. 13%.
- Hammock ParkNearby in Wasl Gate. 82%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)