Aryene Greens construction photos

118 photos taken by Dubai Land Department engineers at 14 site inspections, newest first. The percentage is how much of Aryene Greens was built on the day of each visit.

2 April 202680% built

23 October 202580% built

8 November 202480% built

17 August 202274% built

10 June 202273% built

20 December 202171% built

28 June 202171% built

25 August 202061% built

18 June 201958% built

7 November 201752% built

1 June 201737% built

17 November 201620% built

31 January 201613% built

11 October 201213% built

Back to Aryene Greens construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.