Elwood Estates construction progress
The registered completion date for Elwood Estates in Al Yufrah 1 is June 2028. At the last site inspection, in July 2026, it was 14% built. The developer is Sobha.
14%
Built, at the site inspection of 20 July 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- February 2033
- Construction started
- July 2025
- First registered
- April 2025
- Developer
- Sobha
- Community
- Al Yufrah 1
- Units
- 305
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- إلوود إستيتس
- Project number
- 3602
- Site inspections
- 3
Schedule
Between March 2026 and July 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after its registered date of June 2028.
Site inspections
20 July 2026
14%+4.2 pts
25 March 2026
10%+10 pts
19 March 2025
0%
Context
Al Yufrah 1 has 17 projects under construction, 40% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Elwood Estates?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Elwood Estates handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Elwood Estates?
- Elwood Estates was 14% built at the site inspection on 20 July 2026. The site has been inspected 3 times since March 2025. The Land Department took 22 site photos at its inspections.
- Is Elwood Estates delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Elwood Estates?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Elwood Estates?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- The Valley - RivanaNearby in Al Yufrah 1. 95%, Due March 2027.
- The Valley - NimaNearby in Al Yufrah 1. 80%.
- The Valley - AlanaNearby in Al Yufrah 1. 82%.
- The Valley - Farm Gardens 2Nearby in Al Yufrah 1. 59%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.