Elwood Estates construction progress

The registered completion date for Elwood Estates in Al Yufrah 1 is June 2028. At the last site inspection, in July 2026, it was 14% built. The developer is Sobha.

14%

Built, at the site inspection of 20 July 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
February 2033
Construction started
July 2025
First registered
April 2025
Developer
Sobha
Community
Al Yufrah 1
Units
305
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إلوود إستيتس
Project number
3602
Site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

14%+4.2 pts

  • Elwood Estates construction site, inspection photo 1, 20 July 2026
  • Elwood Estates construction site, inspection photo 2, 20 July 2026
  • Elwood Estates construction site, inspection photo 3, 20 July 2026
  • Elwood Estates construction site, inspection photo 4, 20 July 2026

25 March 2026

10%+10 pts

  • Elwood Estates construction site, inspection photo 1, 25 March 2026
  • Elwood Estates construction site, inspection photo 2, 25 March 2026
  • Elwood Estates construction site, inspection photo 3, 25 March 2026
  • Elwood Estates construction site, inspection photo 4, 25 March 2026

19 March 2025

0%

  • Elwood Estates construction site, inspection photo 1, 19 March 2025
  • Elwood Estates construction site, inspection photo 2, 19 March 2025

All 22 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Elwood Estates?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elwood Estates handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elwood Estates?
Elwood Estates was 14% built at the site inspection on 20 July 2026. The site has been inspected 3 times since March 2025. The Land Department took 22 site photos at its inspections.
Is Elwood Estates delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Elwood Estates?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Elwood Estates?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.