The Valley - Rivana construction photos

67 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of The Valley - Rivana was built on the day of each visit.

5 August 202694% built

22 April 202690% built

6 November 202577% built

4 July 202564% built

10 February 202543% built

2 October 202422% built

22 March 20243.8% built

16 June 20230% built

Back to The Valley - Rivana construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.